Major Capital-Project Challenge: Model Schedule Dependencies and Escalation Together

Challenge project estimates through scope maturity, procurement dependencies and delay costs, distinguishing contingency from duplicated allowances and avoiding universal blowout percentages.

In brief

Trace the estimate to a defined scope and schedule, then test how delays affect labour, equipment, financing and revenue timing. A single contingency percentage cannot replace understanding the project’s risks. Mining, energy and infrastructure projects have different technical, permitting and commercial dependencies that need specific evidence.

Key takeaways

  • Trace cost to scope and schedule.
  • Identify actual critical dependencies.
  • Avoid duplicated contingency and delay costs.
  • Update the estimate with an explained bridge.

Direct answer: Trace the estimate to a defined scope and schedule, then test how delays affect labour, equipment, financing and revenue timing. A single contingency percentage cannot replace understanding the project’s risks. Mining, energy and infrastructure projects have different technical, permitting and commercial dependencies that need specific evidence.

Challenge the basis of estimate

Record design maturity, quantities, productivity, procurement quotes, exchange assumptions and exclusions. Identify long-lead items and the activities that determine completion. Distinguish a supplier’s quoted delivery date from a contractual commitment and a credible integrated schedule.

The GAO estimating guide emphasizes documented assumptions, sensitivity and uncertainty. Apply those methods to the actual project rather than importing a fixed industry-overrun percentage as if it were a forecast.

Build a delay-cost bridge

Suppose a hypothetical project has A$50 million base cost. A four-month critical-path delay adds A$500,000 monthly site overhead, A$200,000 monthly equipment holding cost and A$100,000 monthly incremental financing cost. Direct delay-related additions total A$3.2 million.

If the base estimate already includes A$1 million for those same exposures, only A$2.2 million is additional to that allowance. Separately model delayed operating cash and any price escalation; do not count lost gross revenue as lost profit or assume every delayed activity extends the critical path.

Turn challenge into a management decision

Compare resequencing, alternative procurement, staged commissioning and waiting for better scope definition. Assess safety, environmental and permit requirements as actual constraints, not costs to trade away casually. Assign owners to the assumptions most likely to change the commitment.

Present ranges with their basis and update them as design and procurement mature. Reconcile changes to scope, rates, quantities and risk rather than replacing the old total without explanation. A robust review makes uncertainty manageable; it does not promise that all schedule or cost variance can be eliminated.

Continue the analysis

Sources & further reading

  1. GAO: Cost Estimating and Assessment Guide

    Reliable estimates document scope, assumptions, sensitivity and uncertainty; arbitrary fixed uplifts are not a substitute for risk analysis.

Related topics

  • mining-capex-australia
  • australia
  • fid-governance
  • project-red-teaming
  • infrastructure-risk
Browse more articles
One platform. Two tools.

Research the question.
Build the case.

Use Research Reports to understand the opportunity. Use Executive Editor to develop the recommendation, examine the assumptions and prepare a decision paper.

Research Reports

Explore markets, competitors, customers, brand perception or a product idea. Each one is a complete Standard report.

AI-assisted desk research · One-time report purchaseExplore Research Reports

Executive Editor

Write your case, connect evidence and calculations, review proposed changes and publish a saved version when you are ready.

Use your TDP account · No report purchase requiredExplore Executive Editor