Discount rate

Planning & decisions

A discount rate converts future costs and benefits into present values by reflecting the chosen time-value benchmark and, where appropriate, risk treatment. The rate must match the cash flow's currency, price basis, period, and perspective.

By The Decision Pattern · Updated

A question to consider

Which time-value and risk basis is appropriate for these cash flows and this decision perspective?

Why it matters

The selected rate changes how strongly an analysis favours near-term over later value. An unjustified rate can reverse option rankings or double-count risk already represented in forecast cash flows.

How it works

Choose the rate required by the decision framework or derive a justified financing and risk basis. Match nominal rates with nominal cash flows and real rates with real flows, using consistent period intervals.

How to interpret it

Inspect the source and components of the rate and calculate sensitivity around it. Longer-dated options respond more strongly, so report the undiscounted timing and key uncertainties as well as present values.

Common mistake

Using one convenient percentage for every decision, mixing annual rates with monthly cash flows, or increasing both the rate and downside cash adjustments for the same risk.

Put it to work

Record the rate owner, source, date, inflation basis, risk treatment, and scope, then show how option NPVs change across a justified range.

A practical example

Illustrative example: ₹500,000 received three years from now has a present value of about ₹375,657 at a 10% annual discount rate: ₹500,000 ÷ 1.10³.

Questions worth asking

Is the discount rate the same as inflation?

No. A nominal discount rate may include inflation and other components, while a real rate excludes general inflation; cash flows must match.

Does a higher discount rate always mean higher risk?

Not necessarily. Rate construction depends on the framework, and risk may be modelled in cash flows or scenarios instead of added mechanically.

Sources & further reading

Explore the background to this term. Worked examples on this page are illustrative.