Issue log
Planning & decisions
An issue log is a controlled record of current problems requiring resolution, with each issue's description, impact, owner, priority, actions, due dates, dependencies, status, escalation, and closure evidence. Unlike a risk, an issue has already occurred or presently exists.
By The Decision Pattern · Updated
A question to consider
Which current problem needs ownership, resolution, or escalation before it blocks the intended outcome?
Why it matters
Unrecorded issues are easily discussed repeatedly without ownership or closure. A concise log makes current barriers visible, supports escalation, protects dependent work, and preserves evidence of how the problem was resolved.
How it works
State the observed condition and impact, assign one accountable owner, assess urgency and affected decisions, define the next action and deadline, link dependencies, update status and evidence, and obtain explicit closure.
How to interpret it
Issue count alone is not a health metric. Severity, age, blocked value, recurrence, and resolution quality matter; more reported issues can reflect stronger transparency rather than worse delivery.
Common mistake
Mixing future risks, routine tasks, assumptions, and vague complaints into one list. That creates noise and prevents governance from seeing which existing problems need immediate decisions.
Put it to work
Triage issues on a fixed cadence, escalate when authority or deadline thresholds are crossed, connect each action to a root cause, and close only when outcome evidence exists.
A practical example
Illustrative example: IS-044 records that supplier test data is missing, blocks regulatory submission on Friday, names the procurement lead, sets a 24-hour escalation, and requires accepted files for closure.
Questions worth asking
How is an issue different from a risk?
A risk is an uncertain future event or condition; an issue is a problem that already exists and needs response.
When should an issue be closed?
Close it when agreed resolution evidence exists, affected owners accept the outcome, and any residual risk has been transferred appropriately.
Sources & further reading
Explore the background to this term. Worked examples on this page are illustrative.
- Project Management Institute — Risks vs. issues
The distinction between a future uncertain risk and a current issue, plus the practical fields used to track issues to resolution.
Source checked