Monte Carlo simulation
Planning & decisions
Monte Carlo simulation repeatedly samples specified probability distributions for uncertain inputs and recalculates a model to produce a distribution of possible outcomes. Its usefulness depends on model structure, input evidence, dependencies, and transparent assumptions.
By The Decision Pattern · Updated
A question to consider
What commitment or reserve is justified by the modelled outcome distribution and our tolerance for the upper tail?
Why it matters
A single best-case estimate hides the combined effect of uncertainty across costs, duration, demand, and other drivers. Simulation shows ranges and confidence levels that can support reserves and risk-aware commitments.
How it works
Build a validated deterministic model, identify material uncertain inputs, fit justified distributions and correlations, run enough trials for stable results, inspect output percentiles and tails, and test structural alternatives.
How to interpret it
A percentile is conditional on the model and inputs, not a guarantee. Weak distributions, ignored correlation, omitted risks, or a flawed causal structure can create precise-looking but misleading outputs.
Common mistake
Assigning convenient distributions without evidence, assuming inputs are independent, or presenting the mean as the most likely outcome without inspecting skew and tail exposure.
Put it to work
Document each distribution and dependency, calibrate them with data and accountable judgement, and connect chosen confidence levels to specific reserves or decisions.
A practical example
Illustrative example: 10,000 trials combine uncertain quantities, rates, and schedule delays. The model reports a ₹1.4 million P90 cost, meaning 90% of simulated outcomes are at or below it.
Questions worth asking
Is a P90 outcome guaranteed not to be exceeded?
No. It describes the simulated distribution under the chosen model, inputs, and dependencies; reality can include errors and omitted events.
How is simulation different from sensitivity analysis?
Sensitivity changes inputs to reveal outcome response, while Monte Carlo repeatedly samples probability distributions to estimate a combined outcome distribution.
Sources & further reading
Explore the background to this term. Worked examples on this page are illustrative.
- U.S. GAO — Cost Estimating and Assessment Guide
Monte Carlo simulation for combining input uncertainty into outcome distributions and confidence estimates.
Source checked