Reorder point

Cash & operations

A reorder point is the inventory position that triggers replenishment so new supply can arrive before available stock is exhausted. It typically reflects expected demand during lead time plus a chosen safety buffer.

By The Decision Pattern · Updated

A question to consider

At what inventory position must we order to protect service without buying too early?

Why it matters

Ordering too late can cause stockouts and lost production, while ordering too early ties up cash and space. A defined trigger makes the trade-off reviewable and reduces reliance on memory or urgency.

How it works

Estimate demand during replenishment lead time and add safety stock appropriate to variability and service goals. Define whether the trigger uses on-hand stock or inventory position including open orders and committed demand.

How to interpret it

The point should change when demand patterns, supplier lead time, order schedules, or service requirements change. It is not a universal minimum and may differ by item, location, and season.

Common mistake

Using average demand and average lead time without allowing for variability, or ignoring outstanding purchase orders when deciding whether another order is required.

Put it to work

Recalculate high-value and service-critical items first, document the data window and buffer logic, and connect replenishment quantities to the cash forecast.

A practical example

Illustrative example: expected demand is 20 units per day, replenishment lead time is six days, and safety stock is 40 units. The stated reorder point is 20 × 6 + 40 = 160 units.

Questions worth asking

Does the reorder point include open purchase orders?

That depends on whether the business uses on-hand quantity or inventory position; define the rule explicitly so open orders and committed demand are treated consistently.

How often should a reorder point change?

Review it when demand variability, lead times, service targets, pack sizes, or supply risk change materially, rather than refreshing it only on a calendar.

Sources & further reading

Explore the background to this term. Worked examples on this page are illustrative.

Put the thinking to work.

Explore the question with Research Reports. Write, model and review your decision paper with Executive Editor.

Find your reportExplore Executive Editor