Target costing
Cash & operations
Target costing is a market-driven product-development and cost-management discipline that calculates the maximum allowable unit cost of a new product by subtracting the required profit margin from the competitive market price customers are willing to pay ($ ext{Target Cost} = ext{Target Price} - ext{Target Margin}$), then designs the product and supply chain to meet that ceiling before launch.
By The Decision Pattern · Updated
A question to consider
Given the price target buyers will actually pay and our required margin, what is the maximum unit cost we can design into the bill of materials before tooling?
Why it matters
Between 70% and 85% of a manufactured product's unit cost is locked in during the blueprint and component-selection phase before the first production run ever starts. Traditional cost-plus pricing ("design it first, add up what it costs, and tack on a markup") fails whenever competitors or customer willingness to pay cap the market price.
How it works
First establish the market-allowable selling price and planned volume for the target customer segment through pricing and competitive research. Deduct the required gross or operating margin to establish the allowable unit target cost. Compare that target against the "drifting cost" (what the product would cost using current designs and supplier quotes), decompose the allowable cost across functional subassemblies in proportion to customer value, and use value engineering and cross-functional supplier design reviews to close the cost gap prior to tooling release.
How to interpret it
Under strict target-costing governance, if cross-functional engineering cannot bring the projected unit cost down to the target ceiling without compromising required customer performance, the product is redesigned or canceled rather than launched with broken unit economics.
Common mistake
Closing the target-cost gap on paper by assuming unrealistic production volumes to dilute fixed tooling overhead or squeezing supplier margins without changing part geometry, tolerances, or part count.
Put it to work
Set subassembly cost targets weighted by how much each function matters to the buyer, involve strategic suppliers before freezing CAD drawings, eliminate over-engineered features customers do not value, and freeze tooling release until drifting cost meets target cost.
A practical example
Illustrative example: market research shows a commercial espresso machine must sell at $2,400 to win cafés, and the company requires a 35% gross margin ($840), setting a maximum target cost of $1,560; when initial engineering BOM estimates total $1,790, value engineering consolidates two boiler manifolds and standardizes valves to remove $245 per unit before tooling.
Questions worth asking
How does target costing differ from cost-plus pricing?
Cost-plus starts with production cost and adds a markup to set the price, whereas target costing starts with the market price and subtracts the required margin to cap allowable cost during design.
Why must target costing happen during product design rather than after launch?
Most material, tooling, and assembly costs are locked in once engineering drawings and supplier tooling are finalized, leaving very little room for cost reduction on the shop floor.
Sources & further reading
Explore the background to this term. Worked examples on this page are illustrative.
- Cooper and Slagmulder — Target Costing and Value Engineering (Institute of Management Accountants)
Market-driven target cost derivation, decomposition to component-level targets, and pre-production value engineering.