Capital Rationing Guide: Why Ranking Projects by Profitability Index Can Miss the Best Combination
How to choose projects under a fixed budget when projects are lumpy, and why the best set is not always found by ranking on profitability index.
The short answer
For indivisible investments under a fixed budget, compare total NPV across feasible project combinations, including dependencies and mutual exclusions. A profitability-index ranking can miss the best set even if it uses nearly all the budget. Evaluate the value of specific budget increments instead of assuming a constant value for each extra dollar.
Key takeaways
- Compare feasible combinations when projects are indivisible.
- Include dependencies, mutual exclusions and period-specific budgets.
- A small unspent balance does not establish that a ranking is optimal.
- The value of extra budget can change in discrete steps.
- In the hypothetical example, A+B beats the ranked C+A set by $0.5 million NPV.
How to choose projects under a fixed budget when projects are lumpy, and why the best set is not always found by ranking on profitability index. Key terms used below: opportunity cost, free cash flow, scenario planning, decision criteria. Related guides: Capital Project Evaluation Guide: NPV, IRR, and Payback, and What to Do When They Disagree and Corporate Capital Allocation Framework: Setting Risk-Adjusted Hurdle Rates and ROIC Gates.
What decision this guide supports
When a fixed investment budget is smaller than the cost of the candidate projects, management must choose a feasible set. A return-per-dollar ranking can be useful, but it does not by itself solve every constrained investment problem.
Ranking can solve a simple single-period case when projects are divisible, value scales proportionately with funding and there are no additional interactions or constraints. For indivisible projects, compare feasible combinations. The ICAB investment-appraisal text, section 7.3, explains that distinction and the effect of mutually exclusive projects.
Key terms
- Capital rationing
- A limit on the capital available for investment.
- Profitability index
- The present value of a project's future cash flows divided by its investment.
- Indivisible project
- A project that must be undertaken in full or not at all.
- Value of a budget increment
- The improvement in the best feasible NPV after a specified budget increase. With indivisible projects, it can change in steps rather than at a constant marginal rate.
How to calculate it
The profitability index equals the present value of future cash flows divided by the initial investment, or one plus NPV divided by the investment. For a budget B and indivisible projects, evaluate each combination whose total investment is at most B and add the NPVs. The best combination has the highest total NPV. For a specified increase, calculate the change in the best achievable NPV. Dividing that change by the additional budget gives an average over that interval, not necessarily the marginal value of the next dollar.
Benchmark matrix and working thresholds
The table summarizes the main options or components and what to watch in each.
| Method | What It Does | Strength | Limitation |
|---|---|---|---|
| Rank by profitability index | Funds highest return per dollar first | Simple and quick | Can leave budget unused with indivisible projects |
| Evaluate all combinations | Compares total NPV of feasible sets | Finds the best set | Grows quickly with many projects |
| Integer programming | Optimizes the set under constraints | Handles many projects and constraints | Needs software and clean inputs |
| Stage-gated funding | Releases funds as projects prove out | Reduces risk | Needs clear gates |
Working thresholds
Treat these as starting heuristics to calibrate against your own data, not universal standards.
- Healthy: All feasible combinations compared and the value of added budget quantified.
- Watch closely: Projects ranked by profitability index without checking the combination.
- Act now: Projects funded in the order requested; unused budget left idle with no plan for it.
Worked scenario
The figures below are an illustrative composite, not a named company or an audited case. Replace them with your own data.
A company has a budget of 10 million dollars. Project A costs 4.0 million and has an NPV of 1.2 million, a profitability index of 1.30. Project B costs 6.0 million with an NPV of 1.5 million, an index of 1.25. Project C costs 3.0 million with an NPV of 1.0 million, an index of 1.33. Project D costs 5.0 million with an NPV of 1.1 million, an index of 1.22. Ranking by index funds C, then A, using 7 million for a total NPV of 2.2 million, and neither B nor D fits in the remaining 3 million. Checking combinations shows that A and B together cost exactly 10 million and have an NPV of 2.7 million, 0.5 million more. Other sets are worse: C and B give 2.5 million, A and D give 2.3 million, and C and D give 2.1 million. If the budget rose to 12 million, C, A, and D would cost 12 million and have an NPV of 3.3 million, so the extra 2 million would add 0.6 million of NPV. That figure tells management what a larger budget is worth.
Check every candidate set
| Projects | Investment | NPV | Fits a $10m budget? |
|---|---|---|---|
| None | 0.0 | 0.0 | Yes |
| A | 4.0 | 1.2 | Yes |
| B | 6.0 | 1.5 | Yes |
| A+B | 10.0 | 2.7 | Yes |
| C | 3.0 | 1.0 | Yes |
| A+C | 7.0 | 2.2 | Yes |
| B+C | 9.0 | 2.5 | Yes |
| A+B+C | 13.0 | 3.7 | No |
| D | 5.0 | 1.1 | Yes |
| A+D | 9.0 | 2.3 | Yes |
| B+D | 11.0 | 2.6 | No |
| A+B+D | 15.0 | 3.8 | No |
| C+D | 8.0 | 2.1 | Yes |
| A+C+D | 12.0 | 3.3 | No |
| B+C+D | 14.0 | 3.6 | No |
| A+B+C+D | 18.0 | 4.8 | No |
At an $11 million budget, A+B still provides the best NPV of $2.7 million. At $12 million, A+C+D provides $3.3 million. Thus the first extra $1 million adds no value in this candidate set, while the second enables a $0.6 million gain. The average $0.30 of NPV per additional dollar across the $10m-to-$12m interval is not a constant shadow price.
What the scenario shows
Ranking on index left 3 million idle and 0.5 million of NPV on the table. Comparing combinations, and pricing the value of more budget, is more useful than a simple ranking.
How to read the results
- If the best combination beats the ranked set: Use the combination, and note which assumption would change the choice.
- If a specific budget increase unlocks more value: Compare that gain with financing costs, risks and alternative uses of the funds.
- If leftover funds are small: Do not infer optimality. A different feasible combination can still have a higher NPV even when the ranked set spends the entire budget.
Common failure modes
- Ranking on index alone: With indivisible projects, the ranking can leave part of the budget unused and miss a better set.
- Ignoring the value of unused funds: Specify the real alternative for unspent money, such as retaining liquidity, reducing borrowing or another investment. Do not add an arbitrary cost-of-capital charge on top of NPVs that already reflect appropriately discounted cash flows.
- Treating the budget as fixed forever: A cap can exclude a more valuable combination. Test concrete budget increments rather than assuming the same benefit for every extra dollar.
- Ignoring dependencies between projects: Some projects require or exclude others, which changes the feasible set.
Putting it into practice
- List projects with investment and NPV: Record project and bundle NPVs, indivisibility, dependencies and mandatory commitments. A negative standalone prerequisite can still belong to a positive-value bundle; evaluate that bundle consistently.
- Enumerate feasible combinations: Use a spreadsheet or solver to compute total NPV for each set within the budget.
- Price the budget constraint: Calculate the NPV gain from adding budget and discuss whether to raise the cap.
Sensitivity and limits
- Project NPV estimates: Test the effect of lower NPVs on the best set, since small changes can reorder choices.
- Budget size: Compute the best set at several budget levels.
- Staging options: See whether splitting a project into stages changes the feasible sets.
This example uses certain NPVs and a single-period budget. Real decisions involve uncertain estimates, multi-period budgets, and strategic considerations that are not captured by NPV alone.
Where this fits in a wider decision
Capital rationing belongs in annual planning and in the relationship between corporate finance and business units. Document how the budget was set, revisit it when opportunities change, and review whether the cap reflects real financing limits or conservatism.
Use the analysis in a decision paper
Use the capital allocation reading path to connect the model with the wider investment decision. Record the alternatives, assumptions and sensitivity results in the executive editor.
Your checklist
- Confirm you have avoided this trap: Ranking on index alone.
- Confirm you have avoided this trap: Ignoring the value of unused funds.
- Confirm you have avoided this trap: Treating the budget as fixed forever.
- Confirm you have avoided this trap: Ignoring dependencies between projects.
Steps to follow
List projects with investment and NPV
Record project and bundle NPVs, indivisibility, dependencies and mandatory commitments. Evaluate required prerequisites with the projects they enable.
Enumerate feasible combinations
Use a spreadsheet or solver to compute total NPV for each set within the budget.
Price the budget constraint
Calculate the NPV gain from adding budget and discuss whether to raise the cap.
Common questions
What is capital rationing?
A situation in which the company has less capital than the total needed for all projects with positive NPV, so it must choose among them.
Why can ranking by profitability index give the wrong answer?
Because projects are indivisible, the highest-ranked projects may leave money unspent that a different combination would have used for more total value.
Can the next extra dollar have a different value from a larger budget increase?
Yes. With indivisible projects, a small increase may unlock no new feasible set. A larger increase can enable a better combination. Calculate the best set at each proposed budget rather than applying a constant marginal value.
Related topics
- capital rationing example
- profitability index ranking
- best project combination budget
- indivisible projects NPV
- project selection under budget limit
- capital budgeting constraints
Sources & further reading
- ICAB: Financial Management, investment appraisal section 7.3
Indivisible projects require comparison of feasible combinations, including mutual-exclusion constraints; printed page 59.