Equivalent Annual Cost Guide: Comparing Assets with Different Lives and Costs on a Per-Year Basis
How to choose between assets of unequal life by converting each one's total cost into an equal yearly amount.
The short answer
Equivalent annual cost equals the present value of an asset's costs divided by the annuity factor for its life; a 100,000 machine lasting 5 years with 20,000 yearly running costs costs 46,380 a year, while a 140,000 machine lasting 8 years with 15,000 running costs costs 41,242, so the second is cheaper despite a higher total present cost.
Key takeaways
- Primary measure: Equivalent Annual Cost per Option.
- Healthy: Options compared on equivalent annual cost with salvage values and a realistic replacement chain.
- Watch closely: Options compared on total present cost even though their lives differ.
- Act now: The asset with the lowest purchase price chosen, with running cost and life ignored.
- Machine A has the lower total cost, 175,816 against 220,024, but costs 46,380 a year against 41,242 for machine B, so the longer-lived machine wins by about 5,100 dollars a year.
How to choose between assets of unequal life by converting each one's total cost into an equal yearly amount. Key terms used below: net present value, discount rate, capital expenditure, total cost of ownership. Related guides: Lease vs. Buy Equipment Guide: Present-Value Cost Comparison and the Residual Value Trap and Preventive or Predictive Maintenance: Compare Failure Modes, Safety and Total Cost.
What decision this guide supports
Companies often have to choose between assets that do the same job but have different prices, running costs, and lives. Comparing total present cost is misleading when the lives differ, because the longer-lived asset covers more years of service for its cost.
Equivalent annual cost solves this by converting each option's total cost into a level amount per year over its own life. The option with the lower yearly cost is cheaper to own and operate, on the assumption that the same type of asset can be replaced at the end of its life.
The method is especially useful for replacement decisions on vehicles, machines, and equipment, where purchase price and running cost trade off against each other.
Key terms
- Equivalent annual cost
- The level yearly cost that has the same present value as an asset's total costs.
- Annuity factor
- The present value of one unit paid each year over a given number of years.
- Capital recovery
- The annual amount needed to repay the purchase price with a return over the asset's life.
- Replacement chain
- The assumption that an asset is replaced repeatedly with identical assets.
How to calculate it
The present value of costs equals the purchase price plus the present value of annual running costs, minus the present value of any salvage value. The annuity factor for n years at rate r equals one minus one plus r to the power of minus n, divided by r. The equivalent annual cost equals the present value of costs divided by the annuity factor. It can also be written as the purchase price divided by the annuity factor, which is the capital recovery charge, plus the annual running cost.
Benchmark matrix and working thresholds
The table summarizes the main options or components and what to watch in each.
| Item | Machine A | Machine B |
|---|---|---|
| Purchase price | 100,000 | 140,000 |
| Annual running cost | 20,000 | 15,000 |
| Life (years) | 5 | 8 |
| Present value of costs at 10% | 175,816 | 220,024 |
| Annuity factor | 3.7908 | 5.3349 |
| Capital recovery per year | 26,380 | 26,242 |
| Equivalent annual cost | 46,380 | 41,242 |
Working thresholds
Treat these as starting heuristics to calibrate against your own data, not universal standards.
- Healthy: Options compared on equivalent annual cost with salvage values and a realistic replacement chain.
- Watch closely: Options compared on total present cost even though their lives differ.
- Act now: The asset with the lowest purchase price chosen, with running cost and life ignored.
Worked scenario
The figures below are an illustrative composite, not a named company or an audited case. Replace them with your own data.
Illustrative composite: a company can buy machine A for 100,000 dollars with running costs of 20,000 a year and a life of 5 years, or machine B for 140,000 with running costs of 15,000 and a life of 8 years. There is no salvage value and the discount rate is 10%. The present value of A's costs is 100,000 plus 20,000 times 3.7908, or 175,816. For B it is 140,000 plus 15,000 times 5.3349, or 220,024. Looking only at those totals, A looks cheaper by 44,208 dollars. But B delivers three more years of service. Dividing by the annuity factors, A costs 175,816 divided by 3.7908, or 46,380 dollars per year, and B costs 220,024 divided by 5.3349, or 41,242 per year. Machine B is cheaper by about 5,138 dollars a year. The comparison assumes that the company will keep replacing each machine with another of the same kind, which is reasonable when the need is permanent. If the need is only for 5 years, the comparison changes and requires a salvage value for B at year 5. A check on running cost is also useful: if B's running cost were 22,000 instead of 15,000, its equivalent annual cost would be 48,242, and A would win.
What the scenario shows
Machine A has the lower total cost, 175,816 against 220,024, but costs 46,380 a year against 41,242 for machine B, so the longer-lived machine wins by about 5,100 dollars a year.
How to read the results
- If the longer-lived asset has the lower yearly cost: Buy it, unless the need is short-term.
- If the ranking flips with a small change in the discount rate: The options are close, and other factors such as flexibility should decide.
- If the need is limited in time: Compare costs over the actual period with salvage values.
Common failure modes
- Comparing total present cost for unequal lives: It favors the asset with the shorter life, which only covers fewer years.
- Assuming identical replacement: If technology or prices will change, the repeated-replacement assumption may not hold.
- Ignoring salvage and tax effects: Salvage values, depreciation, and tax shield change the costs of each option.
- Using a single discount rate with no test: The ranking can change when the rate changes, so test it.
Putting it into practice
- List costs and lives: Gather purchase prices, running costs by year, salvage values, and lives for each option.
- Compute annual equivalents: Calculate present value of costs and divide by the annuity factor for each option's life.
- Test the ranking: Vary discount rate, running costs, and the replacement assumption, and check the decision is robust.
Sensitivity and limits
- Discount rate: Test rates of 6%, 10%, and 14%.
- Running cost of machine B: Compare 15,000, 18,000, and 22,000 dollars.
- Salvage value: Check a salvage value of 20,000 for machine B at the end of its life.
The method treats costs as certain and assumes each asset is replaced by an identical one at the end of its life. Taxes, inflation, changing technology, and capacity limits can alter the best choice.
Where this fits in a wider decision
Use equivalent annual cost for repeated replacement decisions on equipment and vehicles. Combine it with maintenance data and technology outlooks.
Your checklist
- Confirm you have avoided this trap: Comparing total present cost for unequal lives.
- Confirm you have avoided this trap: Assuming identical replacement.
- Confirm you have avoided this trap: Ignoring salvage and tax effects.
- Confirm you have avoided this trap: Using a single discount rate with no test.
Steps to follow
List costs and lives
Gather purchase prices, running costs by year, salvage values, and lives for each option.
Compute annual equivalents
Calculate present value of costs and divide by the annuity factor for each option's life.
Test the ranking
Vary discount rate, running costs, and the replacement assumption, and check the decision is robust.
Common questions
What is equivalent annual cost?
It is the present value of an asset's total costs divided by the annuity factor for its life, which gives a level cost per year for comparison.
Why not just compare total costs?
Because assets with different lives provide different years of service, so total cost favors the shorter-lived one.
Related topics
- equivalent annual cost
- eac calculation
- compare assets different lives
- replacement decision npv
- annualized cost of machine
- capital recovery factor
- equivalent annual annuity cost
Sources & further reading
- CFA Institute Research and Learning Resources
CFA Institute
Background on capital budgeting methods, including annuity-based comparisons.
- GAO Cost Estimating and Assessment Guide
U.S. Government Accountability Office
Method guidance for cost estimating and life-cycle cost comparison.
- U.S. Census Bureau Annual Survey of Manufactures
U.S. Census Bureau
Industry data on materials, labor, and value added for manufacturing benchmarks.