How do you document assumptions the client refuses to validate?
Record the assumption, its basis, the requested validation, and the client’s actual response. Identify which conclusions depend on it and show a bounded sensitivity or conditional result. Distinguish factual verification from permission to proceed with uncertainty. Silence, seniority, or acceptance of the deliverable does not validate an unsupported input.
The short answer
Record the assumption, its basis, the requested validation, and the client’s actual response. Identify which conclusions depend on it and show a bounded sensitivity or conditional result. Distinguish factual verification from permission to proceed with uncertainty. Silence, seniority, or acceptance of the deliverable does not validate an unsupported input.
Key takeaways
- Record the stated reason for nonvalidation without inferring motive.
- Separate verified, disputed, unavailable, and accepted-for-analysis states.
- Keep material unvalidated inputs beside the dependent recommendation.
- Agree permitted use and escalation when the missing evidence can change the decision.
A project model assumes that the client has enough operating capacity to implement a recommendation. The relevant owner will not confirm the input. The deadline remains, and the sponsor asks the team to use the number anyway.
The assumption can remain in a conditional analysis, but its status must be clear. In client delivery, document what is known, what was requested, what the client actually said, and how the uncertainty affects the decision.
Clarify what validation was requested
Ask whether the owner is being asked to confirm a source value, approve a forecast, explain an operating condition, or accept a planning assumption. Those are different actions and may require different people.
A finance lead may be able to confirm recorded payroll but not future availability. A sponsor may authorize analysis under uncertainty without being able to verify the underlying operational input.
The AQuA Book discusses formally agreeing assumptions and recording them in a log. For client work, that record should distinguish agreement to use an assumption from evidence establishing its accuracy.
Record the response without assigning a motive
The owner may lack data, disagree with the definition, need another approval, consider the information confidential, or decline the request. Record the stated reason and date. Do not describe a missing response as deliberate obstruction without evidence.
Preserve the exact question and the version of the input that was sent. A response to an earlier number should not be carried forward as validation of a later revision.
If no response arrives, record no response and the follow-up status. Silence is not a verified value or an approval unless a separate authorized process explicitly governs a decision—and even then it does not create factual evidence.
Use status labels that preserve the distinction
| Status | Meaning | Permitted analytical treatment |
|---|---|---|
| Verified | Suitable evidence supports the defined input | Use within its documented scope and period |
| Disputed | A material disagreement remains | Show alternatives or withhold a dependent conclusion |
| Unavailable | The required evidence cannot currently be obtained | Use a clearly labeled scenario if fit for the purpose |
| Accepted for analysis | An authorized owner permits a planning input | Retain the assumption label and sensitivity |
| Superseded | A later version replaces this input | Keep the history and update dependent outputs |
Do not use accepted for analysis as a substitute for verified. Also avoid a generic approved label that leaves readers unable to tell whether the approval concerns facts, method, scope, or the final business choice.
Identify the dependent conclusion
Trace the input to the calculations and recommendations it affects. If the assumption has no material effect on the decision, explain that rather than treating every unresolved field as equally important.
In a fictional example, a proposed service requires 200 tasks at three hours each, or 600 hours. The model assumes 800 available hours, leaving 200 hours of conditional capacity. The owner has not confirmed that availability.
A 500-hour scenario produces a 100-hour shortfall. The useful conclusion is that the proposal requires at least 600 suitably available hours under the stated task assumptions, not that the client definitely has enough capacity.
Check whether the assumption itself is well defined
Headcount, paid hours, scheduled hours, and hours available for this work are different inputs. An owner may refuse to validate a number because it mixes them. Clarify exclusions such as other commitments, absence, training, and required specialist skills.
Likewise, an average handling-time assumption may not apply to new or unusually complex tasks. Do not focus only on validating capacity while leaving the workload estimate unexamined.
Record the source, unit, period, definition, owner, validation request, evidence gap, sensitivity, and next action. A concise register should let another analyst reproduce the conditional result.
Agree the permitted use of unfinished analysis
Put the limitation beside the dependent recommendation in the decision brief. State whether the analysis can support exploration, a limited pilot, a reversible commitment, or no decision until the input is resolved.
If the uncertainty can reverse an irreversible choice, escalate through the agreed authority before presenting the recommendation as ready for use. A footnote does not make an otherwise misleading conclusion acceptable.
When a client chooses to proceed with uncertainty, record who made that choice and the consequence accepted. Preserve the evidence status; do not rewrite the input as confirmed merely because the business decision has been made.
Separate corrections from new work
If the team used the wrong definition or failed to request an essential input, address that analytical problem. If the client requests a new population, geography, or operating model, assess whether the research scope changes.
Use the proposal dependency guide to identify inputs and approvals outside the delivery team's control. Make those dependencies explicit early rather than relying on a late disclaimer.
Do not turn every clarification into scope creep, and do not absorb a material new study without acknowledging its effect on timing and resources. The distinction should follow the agreed question and deliverable.
Keep the record current through delivery
If evidence arrives, update the assumption status, rerun affected calculations, and identify changed conclusions. Retain the previous version so the client can understand why the recommendation moved.
Use the findings-meeting guide when disagreement remains. A working paper in the executive editor should show the assumption, conditional result, unresolved question, and next decision together.
Sources & further reading
- The AQuA Book
The guidance discusses formally agreeing assumptions, recording them in a log, and communicating analytical limitations. The status register and fictional capacity example are original and do not claim full AQuA compliance.