How do you measure project margin when senior review time is missing?
Reconstruct the work needed to deliver the project, including senior review, coordination, and revisions that were never billed separately. Apply a documented cost basis by role, reconcile it with recorded effort and external costs, and calculate margin against the appropriate net fee. Show estimates and exclusions explicitly. Missing time should be investigated before a high reported margin is used to price the next engagement.
The short answer
Reconstruct the work needed to deliver the project, including senior review, coordination, and revisions that were never billed separately. Apply a documented cost basis by role, reconcile it with recorded effort and external costs, and calculate margin against the appropriate net fee. Show estimates and exclusions explicitly. Missing time should be investigated before a high reported margin is used to price the next engagement.
Key takeaways
- Unbilled work still consumes delivery capacity.
- Billing rates are not automatically the correct labor-cost rates.
- Margin and markup use different denominators.
- Including resource costs improves project comparison but does not mean every saved hour reduces payroll.
An advisory project reports a healthy margin because the analyst’s hours and external research costs were recorded. The partner’s evening review and the final revision round never entered the project system. The apparent profitability depends on work being invisible.
A reliable client delivery review connects the fee to all material resources used. It should explain the project’s economics without treating every unbilled hour as free.
Define which margin you are calculating
State the fee basis, included delivery costs, and treatment of overhead. Project contribution after specified delivery costs is different from operating profit after the organization’s wider expenses.
Use net fee after relevant commercial adjustments, with pass-through items handled consistently. Do not compare a fee including reimbursable expenses with costs that omit those same expenses.
Keep collections separate. An unpaid invoice creates a cash and credit issue, but it should not silently change the definition of delivery margin.
Reconstruct the work by activity and role
List research, analysis, synthesis, review, client meetings, coordination, corrections, and final delivery. Identify who performed each activity and whether it was included in the original time record.
ACCA’s activity-based management guidance recommends identifying significant activities, their costs, and relevant drivers. For an advisory project, that can reveal review and coordination effort that a broad analysis category hides.
Use legitimate project records such as review logs, meeting calendars, and document histories to support a reconstruction. A document timestamp alone does not establish continuous hours worked; ask the responsible person to validate estimates and mark their uncertainty.
Use a consistent resource-cost basis
Choose rates that fit the purpose of the analysis and document what they include. Employment-related costs, productive-hour assumptions, and allocated overhead can materially change the result.
A billing rate is a commercial price, not automatically an internal labor cost. Using it as cost can overstate delivery expense unless the analysis explicitly concerns forgone billable opportunity.
Likewise, a senior owner’s time is not economically free because no additional payroll payment occurs. Resource use and incremental cash expense answer different questions and should be shown separately when both matter.
Reconcile a fictional project
| Cost component | Effort and rate | Cost |
|---|---|---|
| Recorded analyst work | 100 hours at 60 | 6,000 |
| Recorded project management | 30 hours at 100 | 3,000 |
| External research | Project-specific expense | 2,000 |
| Missing senior review | 20 hours at 150 | 3,000 |
| Unbilled revisions | 10 analyst hours and 4 senior hours | 1,200 |
| Total | All listed delivery work | 15,200 |
The initial recorded cost is 11,000, implying contribution of 9,000 and a 45% margin. Including senior review raises cost to 14,000 and reduces margin to 30%. Adding the separate revision effort produces cost of 15,200, contribution of 4,800, and a 24% margin.
The rates in this example include assumed employment-related resource costs but exclude general corporate overhead. The result is project contribution on that basis, not company net profit or a claim about cash released by reducing hours.
Check that effort is counted once
Confirm that the senior reviewer is not already included in the management line and that revision hours are additional to the original analyst total. A reconstruction should correct missing work without creating duplicate cost.
Shared meetings need a consistent allocation. If a meeting covers several projects, assigning its full duration to each will overstate effort. If it concerns only one project, spreading it across the portfolio can hide that project’s true demand.
Reconcile subcontractor fees and internal hours too. Work purchased externally should not also appear as internal delivery effort unless the internal line represents genuine coordination or review.
Investigate why the extra work occurred
Separate necessary quality review, correction of the team’s own errors, new client requirements, unclear inputs, and avoidable rework. Those categories have different implications for process improvement and future pricing.
Do not classify every additional hour as scope creep. Some review and correction belong in the original delivery obligation and should have been estimated from the beginning.
A clearer decision brief may reduce ambiguous work. Better source validation or an earlier review point may prevent expensive late revisions without lowering the editorial standard.
Show uncertainty in reconstructed time
If the reviewer can only estimate a range, calculate the resulting margin range and explain the basis. Do not present a reconstructed total to the minute when the records do not support it.
Focus first on material missing activities. An elaborate time reconstruction for tiny tasks can cost more than the decision benefit it provides.
Use the exercise to improve future capture with a small number of meaningful categories. A punitive system can encourage underreporting and make the next margin report less reliable.
Translate the result into a delivery change
The answer may be a different staffing mix, earlier senior involvement, a clearer revision allowance, improved inputs, or a revised fee. Raising the price is not the only possible response.
Use the guides on restricted-data engagements and contradictory client numbers when those issues drive hidden effort.
Before claiming savings from a process change, distinguish time released from payroll reduced. Released senior capacity may be valuable because it enables other work, even if the immediate cash expense remains unchanged.
Preserve the corrected basis for future decisions
Record the original reported margin, added effort, evidence quality, rate basis, and revised result. Keep the explanation so the project can be compared fairly with later engagements.
Use the Executive Editor to present the reconciled economics and the proposed action. A credible margin should survive a review of the work required to produce the deliverable.
Sources & further reading
- ACCA: Activity-based management
Describes identifying significant activities, assigning their costs, and examining appropriate cost drivers. The advisory-project effort and margin reconciliation is original.