How do you prepare a decision paper for an asynchronous review?

Make the paper self-contained, identify the decision authority and required contributors, and provide a dated review baseline with explicit questions and deadlines. Track material comments to a disposition, then record the authorized decision and conditions separately from the discussion.

The short answer

Make the paper self-contained, identify the decision authority and required contributors, and provide a dated review baseline with explicit questions and deadlines. Track material comments to a disposition, then record the authorized decision and conditions separately from the discussion.

Key takeaways

  • A review deadline and a decision deadline serve different purposes.
  • Comments, factual corrections, objections, and approval should have distinct states.
  • Silence does not establish approval unless a valid, explicit process defines it that way.

An asynchronous review lets people examine a decision paper at different times. It works only if the paper and process supply the context that a live meeting would otherwise provide.

For executive decision papers, define what reviewers must decide or contribute, when their input is needed, and how the final choice will be recorded. A shared document and an open comment box are not a complete review process.

State the decision and the requested response

Lead with the question, recommendation, alternatives, consequences, and authority requested. Explain whether the paper seeks factual validation, specialist advice, objection review, or final approval.

Ask specific questions of the relevant reviewers. A finance reviewer may need to check the cash assumptions, while an operations reviewer needs to confirm that the proposed transition is executable.

A general request for thoughts can produce extensive commentary while leaving the important conditions unexamined. The decision brief should make the required contribution easy to identify.

Separate coordination from decision authority

Name the person maintaining the review, the people providing required input, and the authority that makes the decision. Identify others who need the outcome without requiring everyone to approve every detail.

The Atlassian DACI framework is one example that separates coordination, approval, contribution, and informed stakeholders. Use the role distinction where useful while retaining your organization’s actual governance and delegated authority.

Document decision rights explicitly. Editing a paragraph, resolving a comment, or acknowledging receipt should not silently grant authority to commit spending or change a customer promise.

Publish a stable review baseline

Identify the paper version and evidence cutoff. Keep the supporting material accessible to the intended reviewers, with permissions checked before the review window starts.

Include the definitions, units, assumptions, and source locations needed to assess the recommendation without a private explanation from the author. Where supporting detail is lengthy, provide a clear route to it from the relevant claim.

Record material changes during review. Correct errors promptly, but tell affected reviewers what changed and whether their earlier assessment needs to be revisited. A stable baseline should not become a reason to preserve an inaccurate statement.

Set separate review and decision deadlines

Allow time to assess comments before the decision is due. Specify the date, time, and time zone; avoid an ambiguous instruction such as close of business when reviewers work in different locations.

For example, a fictional paper might request required comments by 16:00 UTC on 6 November and reserve a later decision point for resolving material findings. The appropriate interval depends on complexity, availability, and the consequences of the choice.

State what happens if a required reviewer cannot respond. Silence should remain a missing response unless an applicable, explicit process validly defines another consequence. Do not infer approval from a quiet document.

Use a comment register that preserves meaning

Different review comments require different responses
Comment typeExample in a fictional migration paperRequired disposition
Factual correctionThe quoted renewal date differs from the contract recordVerify, correct, and assess the effect on the recommendation
Assumption challengeThe proposed training capacity is unconfirmedObtain evidence or retain an explicit condition
PreferenceA reviewer favors a shorter implementation periodAssess the tradeoff without treating preference as a fact
Material objectionThe fallback cannot support the required customer workResolve or escalate the exposure before the relevant commitment
ApprovalThe authorized person accepts a specified option and conditionsRecord the decision against the reviewed version

For each material comment, retain the owner, evidence, response, and current state. Marking a thread resolved should mean the issue has an explained disposition, not merely that the author wants the discussion to disappear.

Keep discussion focused on the decision

Separate wording improvements from issues that change the options, evidence, obligations, or recommendation. Both can matter, but they should not compete invisibly for the same attention.

Where reviewers disagree, state the competing assumptions and evidence. Avoid summarizing a disagreement as consensus merely because the comments stopped.

If written exchanges become circular or ambiguous, use a focused conversation to resolve the specific issue. Record the resulting reasoning and any remaining dissent in the shared review record so absent participants can assess it.

Handle late evidence without silently restarting the process

Assess whether new information changes the decision, a condition, or only the presentation. Identify who needs to reassess and what commitment must wait for that assessment.

A material correction may justify extending the review or narrowing the approval. A minor wording change may not. The coordinating owner should explain the treatment rather than letting the document drift through unannounced revisions.

The guide on reversible and precedent-setting decisions helps assess the consequences of proceeding. For urgent situations, use the guide on crisis decision briefs to preserve the essential record under time pressure.

Record the outcome separately from the comments

State the option chosen, scope, authority, date, conditions, implementation owner, and review trigger. Link the decision to the paper version and material evidence that informed it.

Identify actions required before implementation and who will verify them. Approval subject to a condition is not evidence that the condition has already been met.

Prepare the paper in the Executive Editor and use the organization’s agreed review channels to manage contributions and approval. The final record should make sense to someone who did not watch the discussion unfold and needs to understand what was actually authorized.

Sources & further reading

  1. DACI Decision-Making Framework — Atlassian Team Playbook

    DACI distinguishes coordination, decision authority, contributions, and informed stakeholders, and records the outcome. Only these role distinctions are used here.

Browse more guides
One platform. Two tools.

Research the question.
Build the case.

Use Research Reports to understand the opportunity. Use Executive Editor to develop the recommendation, examine the assumptions and prepare a decision paper.

Research Reports

Explore markets, competitors, customers, brand perception or a product idea. Each one is a complete Standard report.

AI-assisted desk research · One-time report purchaseExplore Research Reports

Executive Editor

Write your case, connect evidence and calculations, review proposed changes and publish a saved version when you are ready.

Use your TDP account · No report purchase requiredExplore Executive Editor