How do you prepare an investment paper when there is no credible baseline?
State which baseline is missing and why it matters, then construct transparent alternative comparators from the best available evidence. Separate historical observations from the future without-project scenario. Show whether the investment decision changes across credible baselines and propose the smallest evidence-gathering step or bounded commitment needed to resolve a material uncertainty.
The short answer
State which baseline is missing and why it matters, then construct transparent alternative comparators from the best available evidence. Separate historical observations from the future without-project scenario. Show whether the investment decision changes across credible baselines and propose the smallest evidence-gathering step or bounded commitment needed to resolve a material uncertainty.
Key takeaways
- A missing baseline is an evidence gap, not a zero-cost or zero-performance starting point.
- The relevant comparator is what would happen without the proposed investment, which may differ from last year.
- A conditional decision can be more defensible than a precise savings claim built on an invented baseline.
An investment paper often promises savings against the current process. That promise becomes fragile when current cost, volume, service quality, or outcomes are poorly measured. A spreadsheet can still produce a precise return, but the precision may come from an unsupported comparator.
For executive decisions, expose the baseline problem and show what can responsibly be decided despite it. The paper can remain useful without pretending the missing evidence exists.
Identify the baseline that is actually missing
Specify whether the gap concerns current volume, unit cost, failure rate, service level, customer outcome, or the likely future trend. Different gaps require different evidence.
Distinguish an absent record from an inconsistent definition. Several departments may hold cost figures that cover different activities. Reconciling them can be more useful than collecting a new survey.
State how the gap could change the decision. If a proposal is justified primarily by a mandatory requirement, the missing efficiency baseline may affect option selection and funding, even if it does not determine whether some action is necessary.
Define the without-project future
The Green Book describes business as usual as the expected outcome if current arrangements continue without the proposal. It allows qualitative or quantitative description when a monetary expression is not feasible.
For a business paper, this means last year’s actual result is evidence, not automatically the future comparator. Contracts may expire, demand may change, equipment may need replacement, or an already approved improvement may occur anyway.
Separate current observations, committed changes, and uncertain future assumptions. Avoid assigning every favorable future movement to the investment when some would happen without it.
Build an evidence hierarchy for the missing inputs
Start with reconciled operational records, invoices, contracts, and directly observed work where they cover the relevant scope. Use estimates from process owners with their basis and limitations recorded.
Comparable sites or external benchmarks may help bound a scenario, but check differences in service, scale, geography, and accounting boundaries. A benchmark is not your organization’s measured baseline.
A customer story can reveal a mechanism or failure case without estimating its prevalence. The guide on using customer stories appropriately helps keep that distinction visible.
Show alternative comparators explicitly
| Input or result | Low baseline scenario | High baseline scenario |
|---|---|---|
| Annual cases | 10,000 | 10,000 |
| Without-project external cost per case | 8 | 14 |
| Without-project annual cost | 80,000 | 140,000 |
| Proposed annual operating cost | 90,000 | 90,000 |
| Proposed one-time setup cost | 30,000 | 30,000 |
| First-year cost difference favoring the proposal | Negative 40,000 | Positive 20,000 |
The recurring difference before setup ranges from negative 10,000 to positive 50,000. The first-year difference is zero when the without-project cost is twelve per case under these assumptions.
These are fictional scenarios, not a confidence interval. They assume comparable service and that the old charge disappears when the new process starts. Taxes, discounting, inflation, transition overlap, and other consequences are excluded. A full investment appraisal would need the relevant lifecycle and cash-flow treatment.
Ask whether better evidence could change the decision
The example’s ranking changes across the two baseline assumptions, so the unit-cost uncertainty is material. A targeted reconciliation of invoices and case counts may be worth completing before a full commitment.
If all credible baseline scenarios support the same decision, further precision may be less urgent. Still disclose the uncertainty and check whether the funding need, implementation scope, or risk changes even when the preferred option does not.
Do not average incompatible estimates simply to obtain one number. Investigate whether they measure different populations or periods, and retain separate scenarios where the disagreement cannot yet be resolved.
Propose a bounded next commitment
Options include a measurement period, a limited pilot, a staged procurement, or a smaller intervention that remains useful under several baselines. Define what the next step will establish and how its result changes the later decision.
Budget the evidence-gathering work and the consequence of delay. Waiting is not free if the current arrangement creates continuing costs or missed deadlines. Conversely, urgency does not make an invented baseline credible.
Clarify decision rights for approving a limited investigation versus authorizing the full investment. Make sure the paper’s recommendation matches the authority being requested.
Keep unmeasured outcomes in the comparison
Some consequences may be important without a defensible monetary value. Describe service reliability, customer burden, accessibility, or operational resilience with the best available evidence and explicit limits.
Do not set an unmeasured benefit to zero and then claim the cash model fully represents value. Do not invent a monetary value simply to make the benefit fit the spreadsheet either.
Use a separate evidence table for nonmonetized consequences, indicating direction, affected parties, supporting observations, and uncertainty. Explain how these considerations affect the recommendation alongside the financial scenarios.
Write the recommendation with its conditions
Prepare a decision brief that names the missing baseline, alternative comparators, decision sensitivity, proposed commitment, and evidence required before the next stage.
Use the guide on auditable board appendices for the underlying records and calculations. Assemble the paper in the Executive Editor so the main recommendation remains readable while reviewers can trace its assumptions.
The paper succeeds when decision-makers understand what is supported, what remains uncertain, and which commitment the evidence can justify now.
Sources & further reading
- HM Treasury: The Green Book 2026
Business as usual is the expected outcome without the proposal and provides the comparator; where monetary expression is infeasible, the baseline may be quantitative or qualitative.