How do you write the implementation section of an approval paper?

Describe the first authorized action, accountable owners, required capacity, dependencies, delivery sequence and evidence needed at the next checkpoint. Separate approval from readiness to start, and identify which later commitments require another decision. Include acceptance, operational ownership and the consequences of delay so the reader can assess whether the recommendation is executable.

The short answer

Describe the first authorized action, accountable owners, required capacity, dependencies, delivery sequence and evidence needed at the next checkpoint. Separate approval from readiness to start, and identify which later commitments require another decision. Include acceptance, operational ownership and the consequences of delay so the reader can assess whether the recommendation is executable.

Key takeaways

  • Approval does not make unconfirmed people, access or funding available.
  • Name both the delivery owner and the owner of each external dependency.
  • A checkpoint should specify evidence and a decision, not only a meeting date.
  • Implementation ends with accepted operational ownership, not merely a completed project task.

An executive paper recommends a new operating process and ends with a sentence saying implementation will begin after approval. The business case is persuasive, but the analyst, source-data owner and receiving operations team have not agreed to the work. The recommendation has a destination without an executable route.

The implementation section should let the approver understand what the decision will authorize, what must happen before work starts and how the organization will know whether the change is ready to use. It does not need to reproduce every project task.

Start with the action that approval actually permits

State whether the request authorizes discovery, a limited trial, a contract, a full rollout or another bounded commitment. Identify any conditions that must be met before the next stage begins.

Do not use one approval label to cover materially different decisions. Permission to investigate a replacement does not necessarily permit shutting down the current process. Approval of a spending limit does not establish that every dependency is ready or every contract has been authorized.

Connect this boundary to the decision rights that apply in the organization. The paper should describe the authority requested rather than inventing a new governance process in its implementation paragraph.

Use a compact delivery worksheet

GovS 002 Project Delivery links planning to accountability, dependencies, resources and the confidence of estimates. It also treats transition and ongoing responsibility as part of delivery. The following worksheet adapts those disciplines for an approval paper; its use does not imply that private organizations fall within the standard's mandatory government scope.

Suggested implementation content for an executive paper
ElementWhat the approver needs to know
First authorized stepThe specific commitment that follows approval
Accountable ownerWho is responsible for coordinating delivery and resolving issues
ResourcesPeople, skills, funds and operating capacity actually required
DependenciesWhat another team or organization must supply, and by when
Sequence and timingWhich activities can overlap and which must wait
Checkpoint evidenceWhat establishes readiness for the next commitment
Acceptance and operationWho accepts the result and owns it after transition

Use an appendix or linked delivery plan for detailed tasks. Keep any condition that could change approval in the main paper rather than hiding it in a large schedule.

Describe a fictional implementation before promising a date

Suppose an organization proposes a new monthly reporting workflow. The analyst must map the source fields, configure the transformation and reconcile the resulting report. The source-data owner must provide an approved extract, while the operating team must agree the report definition and acceptance evidence.

Assume mapping needs sixteen analyst hours, configuration twenty-four and reconciliation twenty: sixty in total. The analyst has twelve hours a week genuinely available for this work. Even before considering task order and external delays, the work requires at least five weeks of that analyst's capacity.

A four-week promise would therefore need a credible change in resources, scope or method. Merely naming the analyst in the paper does not create additional capacity. Adding another person also does not automatically divide elapsed time in half if the tasks need specialist knowledge or must happen sequentially.

The example is a capacity check, not a complete schedule. Data access, review availability and correction cycles can make the actual elapsed period longer.

Give dependencies owners and evidence

A dependency entry should say what is needed, who controls it, when it is needed and how fulfillment will be confirmed. Data available is weaker than identifying the approved extract, required fields, access route and responsible owner.

Separate an agreed dependency from an assumption awaiting confirmation. If a supplier has not committed to a delivery date, mark the date as conditional and explain what happens if it moves.

Check for circular dependencies. The operations team may be waiting for a finished report before defining acceptance, while the analyst needs that definition to build the report. The implementation plan should resolve the sequence rather than repeating both tasks in a list.

Make checkpoints capable of changing the next step

For the fictional workflow, a useful checkpoint might require a reconciled trial report, documented exceptions and confirmation from the receiving owner that the output is usable. The decision at that checkpoint could be to begin limited operation, correct specified defects or stop the proposed transition.

A progress meeting alone is not the acceptance evidence. Define what will be inspected, who can judge it and what unresolved findings prevent the next commitment.

Keep criteria proportionate to the consequence of failure. Do not introduce universal percentages or arbitrary numbers of successful cycles. Explain why the chosen evidence is sufficient for the particular operating decision and what uncertainty remains.

Show the response to delay and failure

Identify which activity moves if a dependency is late, which benefits are delayed and which costs continue. A schedule shift may affect some outcomes without moving every line of the business case equally.

State the permitted fallback, such as continuing the existing process for a defined period, using a narrower scope or returning for a revised decision. Confirm that the fallback has an owner and resources. A fallback described only as revert if necessary can conceal its own technical or commercial constraints.

Record escalation conditions and the person responsible for bringing them to the decision-maker. An implementation owner should not have to infer whether a major cost or scope change still falls within the original approval.

Plan for the operating owner to accept the change

Identify training, documentation, access, maintenance and support needed after launch. Confirm who owns recurring costs and who investigates defects after the project team leaves.

Acceptance should mean the relevant owner has the evidence and capability to use the result under the agreed conditions. A file being delivered or a configuration being deployed is not automatically operational acceptance.

Keep the baseline plan and changes traceable. Use the guide to changed decisions versus changed forecasts when delivery information changes. Use assessing the paper after approval to learn whether the original implementation section gave the organization what it needed.

The executive decisions hub provides related methods. In the executive editor, keep the decision brief explicit about the authorized action, confirmed resources, unresolved dependencies and next evidence-based checkpoint.

Sources & further reading

  1. Government Project Delivery: GovS 002 Project Delivery, version 2.1

    Sections 7.2 and 7.4 address planning, ownership, dependencies, estimates and resource constraints; the principles include transition with accepted ongoing responsibilities.

Browse more guides
One platform. Two tools.

Research the question.
Build the case.

Use Research Reports to understand the opportunity. Use Executive Editor to develop the recommendation, examine the assumptions and prepare a decision paper.

Research Reports

Explore markets, competitors, customers, brand perception or a product idea. Each one is a complete Standard report.

AI-assisted desk research · One-time report purchaseExplore Research Reports

Executive Editor

Write your case, connect evidence and calculations, review proposed changes and publish a saved version when you are ready.

Use your TDP account · No report purchase requiredExplore Executive Editor