IRR vs MIRR Guide: Why the Reinvestment Assumption Can Reverse a Project Ranking
How the internal rate of return assumes that cash is reinvested at the IRR itself, and how the modified IRR and NPV give a more realistic ranking.
The short answer
IRR implicitly assumes each cash inflow is reinvested at the IRR, which flatters projects that return cash early; project A with 400 a year for four years has an IRR of 21.9% against 18.9% for project B, which pays 2,000 in year four, but at a 10% cost of capital B has the higher NPV, 366 against 268.
Key takeaways
- Primary measure: NPV, IRR, and Modified IRR for Each Project.
- Healthy: Projects ranked on NPV with IRR and MIRR shown for context, and reinvestment assumptions stated.
- Watch closely: Projects ranked on IRR alone, with NPV mentioned as a check.
- Act now: Mutually exclusive projects chosen on the highest IRR, favoring short, quick-return projects that destroy more value.
- IRR ranks project A first at 21.9% against 18.9%, but B adds 366 of NPV against 268, and the MIRR of 18.9% against 16.7% agrees with NPV.
How the internal rate of return assumes that cash is reinvested at the IRR itself, and how the modified IRR and NPV give a more realistic ranking. Key terms used below: internal rate of return, net present value, payback period, discount rate. Related guides: NPV, IRR and Payback: Resolve Conflicting Project Rankings with the Actual Decision and Capital Rationing Guide: Why Ranking Projects by Profitability Index Can Miss the Best Combination.
What decision this guide supports
The internal rate of return is popular because it expresses a project's value as a single percentage. But it has a hidden assumption: the cash a project returns before its end is reinvested at the IRR itself. A project with a very high IRR is assumed to be able to reinvest at that same high rate, which may not be possible.
This assumption can change a ranking. A project that returns cash early may have a higher IRR than one that returns more cash later, even if the second adds more value at the company's cost of capital.
The modified IRR addresses this by assuming reinvestment at a stated rate, usually the cost of capital, and financing at a stated rate. NPV avoids the problem by discounting at the cost of capital.
Key terms
- Internal rate of return
- The discount rate at which a project's NPV is zero.
- Modified IRR
- A return measure that assumes inflows are reinvested at a stated rate.
- Reinvestment assumption
- The rate at which a measure assumes interim cash is put to work.
- Mutually exclusive projects
- Projects of which only one can be chosen.
How to calculate it
The IRR is the rate at which the NPV of the project's cash flows equals zero. The NPV equals the sum of cash flows divided by one plus the cost of capital to the power of their year. The modified IRR equals the future value of positive cash flows, compounded at the reinvestment rate to the end of the project, divided by the present value of negative cash flows at the financing rate, raised to one divided by the number of years, minus one.
Benchmark matrix and working thresholds
The table summarizes the main options or components and what to watch in each.
| Measure | Project A | Project B |
|---|---|---|
| Cash flows (year 0 to 4) | -1,000, 400, 400, 400, 400 | -1,000, 0, 0, 0, 2,000 |
| IRR | 21.9% | 18.9% |
| NPV at 10% | 268 | 366 |
| MIRR at 10% reinvestment | 16.7% | 18.9% |
| Ranking by IRR | First | Second |
| Ranking by NPV or MIRR | Second | First |
Working thresholds
Treat these as starting heuristics to calibrate against your own data, not universal standards.
- Healthy: Projects ranked on NPV with IRR and MIRR shown for context, and reinvestment assumptions stated.
- Watch closely: Projects ranked on IRR alone, with NPV mentioned as a check.
- Act now: Mutually exclusive projects chosen on the highest IRR, favoring short, quick-return projects that destroy more value.
Worked scenario
The figures below are an illustrative composite, not a named company or an audited case. Replace them with your own data.
Illustrative composite: a company can invest 1,000 in only one of two projects, and its cost of capital is 10%. Project A returns 400 each year for four years. Project B returns nothing for three years and 2,000 in year four. The IRR of A is 21.9% and that of B is 18.9%, so a ranking by IRR picks A. The NPV of A at 10% is 400 times 3.1699, minus 1,000, or about 268. The NPV of B is 2,000 divided by 1.4641, minus 1,000, or about 366. B adds about 98 more value. The IRR of A hides the fact that its early cash must be reinvested somewhere. If reinvested at 10%, the four payments of A grow to 1,856 by year 4, and the modified IRR is 1,856 divided by 1,000, to the power of one quarter, minus one, or 16.7%, which is below B's 18.9%. B's single payment needs no reinvestment, so its MIRR equals its IRR. If the company could reinvest A's cash at 21.9%, A would be better, but few companies can find opportunities that good on demand. The decision should rely on NPV for mutually exclusive projects and treat IRR as a communication tool.
What the scenario shows
IRR ranks project A first at 21.9% against 18.9%, but B adds 366 of NPV against 268, and the MIRR of 18.9% against 16.7% agrees with NPV.
How to read the results
- If IRR and NPV rankings disagree: Trust NPV at a realistic cost of capital, and check the crossover rate.
- If MIRR is much lower than IRR: The project's attractiveness relies on reinvesting early cash at a high rate.
- If both measures agree: The ranking is robust to the reinvestment assumption.
Common failure modes
- Ranking exclusive projects on IRR: IRR can favor smaller or shorter projects that add less total value.
- Assuming reinvestment at a high IRR: Few firms can reinvest at very high rates, so IRR overstates returns.
- Ignoring multiple IRRs: Projects with changing signs of cash flow can have more than one IRR, or none.
- Using MIRR without a stated reinvestment rate: The result depends on the rate chosen, and it must be justified.
Putting it into practice
- Compute NPV, IRR, and MIRR: Show all three, with the cost of capital and reinvestment rate stated.
- Compare mutually exclusive projects on NPV: Rank by NPV, or by profitability index under capital rationing.
- Explain differences: When rankings differ, show why using reinvestment and timing, and record the decision.
Sensitivity and limits
- Reinvestment rate: Test MIRR with reinvestment at 6%, 10%, and 15%.
- Cost of capital: Compare NPV at 8%, 10%, and 15%, and note the crossover rate.
- Timing of cash flows: Check how moving a payment from year 4 to year 3 changes the ranking.
NPV, IRR, and MIRR all rely on forecast cash flows and a chosen cost of capital. MIRR depends on the reinvestment assumption, and no single measure captures risk, flexibility, or strategic value.
Where this fits in a wider decision
Use NPV as the main criterion, show IRR for communication and MIRR as a check on reinvestment. Document the cost of capital and any reinvestment assumption in the investment paper.
Your checklist
- Confirm you have avoided this trap: Ranking exclusive projects on IRR.
- Confirm you have avoided this trap: Assuming reinvestment at a high IRR.
- Confirm you have avoided this trap: Ignoring multiple IRRs.
- Confirm you have avoided this trap: Using MIRR without a stated reinvestment rate.
Steps to follow
Compute NPV, IRR, and MIRR
Show all three, with the cost of capital and reinvestment rate stated.
Compare mutually exclusive projects on NPV
Rank by NPV, or by profitability index under capital rationing.
Explain differences
When rankings differ, show why using reinvestment and timing, and record the decision.
Common questions
What is the difference between IRR and MIRR?
IRR assumes cash is reinvested at the IRR itself, while MIRR assumes reinvestment at a stated rate such as the cost of capital.
Why can IRR and NPV give different rankings?
Because IRR ignores project scale and assumes high reinvestment rates, while NPV measures added value at the cost of capital.
Related topics
- irr vs mirr
- reinvestment assumption irr
- modified internal rate of return
- irr npv conflict
- mirr calculation example
- project ranking irr npv
- irr limitations
Sources & further reading
- CFA Institute Research and Learning Resources
CFA Institute
Background on NPV, IRR, and MIRR and the reinvestment assumption.
- GAO Cost Estimating and Assessment Guide
U.S. Government Accountability Office
Method guidance for cost estimating and comparing alternatives.
- Federal Reserve Selected Interest Rates (H.15)
Board of Governors of the Federal Reserve System
Benchmark interest rates used to set discount rates and compare financing costs.