Job Sequencing Guide: Comparing First-Come, Shortest-Time, Earliest-Due-Date, and Critical-Ratio Rules
How different job sequencing rules change average completion time and lateness on one machine or team, and which to use when.
The short answer
On a single resource, shortest processing time minimizes average flow time and earliest due date minimizes maximum lateness; for four jobs, first-come order gives an average flow time of 11.25 with two late jobs, while shortest-time and earliest-due-date orders both give 8.75 with none late.
Key takeaways
- Primary measure: Average Flow Time, Number of Late Jobs, and Total Lateness.
- Healthy: A sequencing rule chosen for the business goal, tested on real queues, and applied consistently with exceptions logged.
- Watch closely: Jobs run in the order received, with expediting when customers complain.
- Act now: Sequences changed constantly by whoever shouts loudest, so lead times and lateness are unpredictable.
- Reordering the same 18 hours of work cut average flow time from 11.25 to 8.75 hours and removed all lateness, though critical ratio, which adapts as time passes, left one job 1 hour late.
How different job sequencing rules change average completion time and lateness on one machine or team, and which to use when. Key terms used below: cycle time, work in progress, throughput, capacity planning. Related guides: Little's Law Guide: Linking Work in Process, Throughput, and Cycle Time to Shorten Lead Times and Value a Bottleneck Improvement by the Additional Good Output the Business Can Sell.
What decision this guide supports
When several jobs wait for the same machine, technician, or team, someone must decide the order. The choice does not change the total time to finish all the work, but it changes when each job finishes, and so the average wait and the number of late deliveries.
Simple dispatching rules are easy to apply. First-come, first-served is fair but ignores job length and urgency. Shortest processing time runs short jobs first. Earliest due date runs the most urgent jobs first. Critical ratio compares the time left until a job is due with the work it still needs.
No rule is best for every goal. The right one depends on whether the aim is a fast average turnaround, few late jobs, or protection of the most urgent customers.
Key terms
- Dispatching rule
- A simple rule for choosing which waiting job to start next.
- Flow time
- The time from a job's availability to its completion.
- Lateness
- The amount by which a job's completion exceeds its due date.
- Critical ratio
- Time remaining to the due date divided by processing time remaining.
How to calculate it
The completion time of a job equals the sum of the processing times of all jobs sequenced up to and including it. Flow time equals completion time when all jobs are available at time zero. Lateness equals the larger of zero and completion time minus due date. Critical ratio equals time remaining until the due date divided by processing time remaining; a ratio below one means the job is behind schedule.
Benchmark matrix and working thresholds
The table summarizes the main options or components and what to watch in each.
| Rule | Order | Average Flow Time | Late Jobs | Total Lateness |
|---|---|---|---|---|
| First come, first served | A, B, C, D | 11.25 | 2 | 12 |
| Shortest processing time | B, D, A, C | 8.75 | 0 | 0 |
| Earliest due date | B, D, A, C | 8.75 | 0 | 0 |
| Critical ratio (dynamic) | B, A, D, C | 9.25 | 1 | 1 |
Working thresholds
Treat these as starting heuristics to calibrate against your own data, not universal standards.
- Healthy: A sequencing rule chosen for the business goal, tested on real queues, and applied consistently with exceptions logged.
- Watch closely: Jobs run in the order received, with expediting when customers complain.
- Act now: Sequences changed constantly by whoever shouts loudest, so lead times and lateness are unpredictable.
Worked scenario
The figures below are an illustrative composite, not a named company or an audited case. Replace them with your own data.
Illustrative composite: four jobs arrive together at one machine. Job A takes 5 hours and is due at hour 10, B takes 2 and is due at 4, C takes 8 and is due at 20, and D takes 3 and is due at 9. Total work is 18 hours whichever order is used. In arrival order, A, B, C, D finish at hours 5, 7, 15, and 18, an average flow time of 11.25. Job B is late by 3 hours and job D by 9, so two jobs are late and total lateness is 12 hours. With shortest processing time, the order is B, D, A, C, finishing at 2, 5, 10, and 18, an average of 8.75, and all four jobs meet their due dates. Here the earliest-due-date order is the same, so the results match. The critical ratio rule recalculates as jobs finish. At the start, A and B tie at 2.0, and B goes first. At hour 2, A has a ratio of 1.6, C of 2.25, and D of 2.33, so A goes next. At hour 7, D has a ratio of 0.67 and C of 1.63, so D goes before C. The order is B, A, D, C, finishing at 2, 7, 10, and 18, an average of 9.25, with job D late by 1 hour. The result shows that reordering the same work can cut average waiting by about 22% and eliminate lateness, but different rules can disagree when jobs and due dates differ.
What the scenario shows
Reordering the same 18 hours of work cut average flow time from 11.25 to 8.75 hours and removed all lateness, though critical ratio, which adapts as time passes, left one job 1 hour late.
How to read the results
- If average flow time matters most: Use shortest processing time, with a guard against starving long jobs.
- If due dates matter most: Use earliest due date or critical ratio.
- If rules give very different results: The queue is under pressure, and capacity or due-date promises may need review.
Common failure modes
- Always running short jobs first: Long jobs can wait indefinitely, so add an aging rule or limit.
- Ignoring due dates: Rules that minimize average time may still miss important commitments.
- Changing the sequence ad hoc: Frequent expediting makes lead times unpredictable and wastes time on setups.
- Ignoring setup times: Sequence-dependent setups can outweigh the benefits of a processing-time rule.
Putting it into practice
- Define the goal: Decide whether to prioritize average speed, on-time delivery, or protection of key customers.
- Test rules on real queues: Simulate rules on recent job data and compare flow time, lateness, and fairness.
- Apply and monitor: Adopt a rule with clear exceptions, publish it, and review the results each month.
Sensitivity and limits
- Due-date tightness: Compare results when all due dates are 20% earlier.
- Job mix: Test a queue with one very long job.
- Setup times: Check the effect of a 1-hour setup between jobs of different types.
The example has one machine, jobs available at once, known processing times, and no setups. Real shops have arrivals over time, uncertain times, several machines, and priorities beyond due dates.
Where this fits in a wider decision
Use dispatching rules for repair shops, job shops, service desks, and any single-resource queue. Combine them with capacity management and honest due-date quoting.
Your checklist
- Confirm you have avoided this trap: Always running short jobs first.
- Confirm you have avoided this trap: Ignoring due dates.
- Confirm you have avoided this trap: Changing the sequence ad hoc.
- Confirm you have avoided this trap: Ignoring setup times.
Steps to follow
Define the goal
Decide whether to prioritize average speed, on-time delivery, or protection of key customers.
Test rules on real queues
Simulate rules on recent job data and compare flow time, lateness, and fairness.
Apply and monitor
Adopt a rule with clear exceptions, publish it, and review the results each month.
Common questions
Which job sequencing rule is best?
It depends on the goal: shortest processing time minimizes average flow time, earliest due date minimizes maximum lateness, and critical ratio adapts to urgency.
Does the sequence change the total time to finish all jobs?
No, on one machine the total is the same, but the completion time of each job and the lateness differ.
Related topics
- job sequencing rules
- spt vs edd
- critical ratio scheduling
- dispatching rules example
- minimize average flow time
- single machine scheduling
- fifo vs shortest processing time
Sources & further reading
- NIST Manufacturing Extension Partnership
National Institute of Standards and Technology
Public resources for manufacturers on scheduling and flow improvement.
- ASCM Supply Chain Resources
Association for Supply Chain Management
Industry definitions for scheduling, lead time, and dispatching.
- U.S. Census Bureau Annual Survey of Manufactures
U.S. Census Bureau
Industry data on materials, labor, and value added for manufacturing benchmarks.