Market size
Indonesia produced about 790 million tonnes of coal in 2025, according to Ministry of Energy and Mineral Resources (ESDM/MEMR) figures reported by Argus and Databoks. That was down 5.5% from the 2024 record of about 836 million tonnes, the first fall since 2020, but still above the 2025 target of about 740 million tonnes.
The ministry's data appears in two versions. A SXCoal summary republished by the coal association APBI-ICMA gives 817.48 million tonnes of "final" 2025 output and exports of 523.35 million tonnes, but its components sum to more than production, so we headline 790 million tonnes and show 817 million tonnes as the top of the range.
In value terms, the Central Statistics Agency (BPS) recorded coal exports of $30.53bn in 2025, down 20.5%, on 529 million tonnes. About a third of output is sold at home, with power-sector coal capped at $70 a tonne.
| Measure | 2024 | 2025 | Change | Source |
|---|---|---|---|---|
| Production | 836 Mt | 790 Mt | −5.5% | MEMR via Argus, Databoks |
| Exports (volume, ministry) | about 558 Mt | 514 Mt | −7.9% | MEMR via Argus |
| Exports (volume, customs) | 566 Mt | 529 Mt | −6.4% | BPS via SXCoal/APBI |
| Export value | $37.77bn | $30.53bn | −20.5% | MEMR (2024) via Tempo; BPS (2025) |
| Domestic market obligation sales | – | 254 Mt | – | MEMR via Argus |
| Argus GAR 4,200 price, fob Kalimantan | – | $44.99/t (24 Dec) | −71% from 2021 peak | Argus |
Market structure
- Buyers. China took 213 million tonnes (40.2% of exports, $10.22bn) and India 105 million tonnes (14.3%, $5.22bn) in 2025; both cut purchases.
- Domestic use. Power stations used about 141 million tonnes and smelters about 76 million tonnes in 2025 under the domestic market obligation, which requires miners to sell at least 25% of output at home.
- Bumi Resources (KPC and Arutmin) sold 74.6 million tonnes in 2025, down 2%, at an average FOB price of $59.7 a tonne, down 17%; consolidated revenue fell 15.9% to $4.81bn. It guides 76 to 78 million tonnes for 2026.
- Alamtri Resources Indonesia (formerly Adaro Energy) reported 2025 revenue of $1,874m, down 10%, and coal sales of 6.28 million tonnes, with the average selling price down 25%. Its volumes are much smaller than Bumi's and the two are not directly comparable.
- Policy. The government is setting the 2026 production target below 700 million tonnes (the APBI page cites work plans of about 600 million tonnes) after assessing domestic needs.
How this estimate was made
- The headline is the ministry's 790 million tonne production figure, reported by Argus (8 January 2026) and Databoks (2 February 2026). Tonnes are the standard measure for this market.
- The range runs to 817.48 million tonnes, the alternative ministry total on the APBI-ICMA page. We note its internal inconsistencies rather than choose between the two.
- Export volume differs by source: 514 million tonnes (ministry) against 529 million tonnes (BPS customs data). The $30.53bn export value is BPS; the 2024 comparison of $37.77bn comes from a ministry presentation reported by Tempo, so the two years are not strictly like for like.
- The 2024 production and export volumes in the table are derived from Argus's percentage changes (our calculation), except where the Tempo and SXCoal pages give them directly (836.1 Mt and 566 Mt).
- The forecast is the government's stated intention, not a market forecast. The only independent 2026 figure found is the IEA's 721 million tonne demand projection cited by Ember.
Questions
How much coal does Indonesia produce?
About 790 million tonnes in 2025, down 5.5% from a record 836 million tonnes in 2024, according to the energy ministry.
How much coal does Indonesia export and to whom?
Between 514 and 529 million tonnes in 2025, worth $30.53bn (BPS). China took 213 million tonnes and India 105 million tonnes.
Who are Indonesia's largest coal miners?
Bumi Resources sold 74.6 million tonnes in 2025 through KPC and Arutmin, with revenue of $4.81bn. Alamtri (formerly Adaro Energy) had revenue of $1,874m.
Will Indonesian coal production fall in 2026?
The government plans a 2026 production target below 700 million tonnes, from 790 million tonnes in 2025, and the IEA expects demand for Indonesian coal to fall to 721 million tonnes.
Sources
- Indonesian coal output, exports decline in 2025, Argus Media, 8 January 2026.
- Indonesia's coal production decreased in 2025, Databoks (Katadata), 2 February 2026.
- Indonesia's coal output hits record 817 Mt in 2025, over 60% exported, APBI-ICMA (republishing SXCoal), 19 May 2026.
- Review: Indonesia 2025 coal exports end 5-yr uptrend, APBI-ICMA (republishing SXCoal, BPS data), 5 February 2026.
- Indonesia's coal output hits 584 million tons in 2025, misses annual target, Tempo, 6 November 2025.
- Bumi Resources raih laba bersih US$81 juta pada 2025, Kontan, 30 March 2026.
- Alamtri Resources Indonesia FY25 public expose, PT Alamtri Resources Indonesia Tbk, early 2026.
- Indonesia's coal sector at a crossroads as output set to fall, Ember, updated 13 April 2026.