Market size
Mordor Intelligence values the US power transformer market at $4.49bn in 2025, rising to $6.39bn by 2031 at 6.08% a year. Its scope covers high-voltage units for transmission and substations, and excludes distribution and small pole-mounted transformers.
No official body publishes a US market value for transformers, so every dollar figure here comes from paid-report publishers. Research and Markets puts the whole US transformer market at $12.2bn in 2024, with distribution transformers taking more than 69%. The remaining share is about $3.8bn by our calculation, which sets the low end of the range. DataM Intelligence gives $8.94bn for 2025, but that figure covers low and medium-voltage transformers only, so it measures a different market.
Wood Mackenzie estimates that demand for power transformers has risen 116% since 2019, that supply will fall 30% short of demand in 2025, and that imports will make up about 80% of US power transformer supply.
| Measure | Value | Period | Source |
|---|---|---|---|
| Power transformer market | $4.49bn | 2025 | Mordor Intelligence |
| All US transformers | $12.2bn | 2024 | Research and Markets |
| Power transformer supply shortfall | 30% | 2025 | Wood Mackenzie |
| Imports' share of power transformer supply | about 80% | 2025 | Wood Mackenzie |
What drives it
- Demand has outrun supply. Wood Mackenzie data cited by POWER Magazine shows demand up 119% for power transformers and 274% for generator step-up units since 2019.
- Prices and lead times have risen sharply. Unit prices for power transformers are up 77% since 2019. Lead times averaged 128 weeks in Wood Mackenzie's second-quarter 2025 survey, and 144 weeks for generator step-up units.
- Electricity use is growing again. US consumption has risen 7% since 2020, after falling 1% between 2010 and 2020.
- An ageing installed base. NREL estimates 60 million to 80 million distribution transformers are in service, with more than 3 TW of capacity. It projects that capacity may need to grow 160% to 260% by 2050 compared with 2021.
- New domestic factories. Manufacturers have committed about $1.8bn to North American capacity since 2023. Hitachi Energy has put $457m into South Boston, Virginia and Siemens Energy $150m into a large power transformer plant in Charlotte, North Carolina.
How this estimate was made
- The headline is Mordor Intelligence's 2025 figure, because it defines its scope as power transformers and excludes distribution units.
- For the low end we took Research and Markets' $12.2bn total for 2024 and removed the distribution share: 31% of $12.2bn is about $3.8bn. This is our calculation; the remainder may include some non-power units.
- Confidence is low: only paid-report publishers give dollar values, and they use different scopes. Wood Mackenzie, NREL and DOE give volume and supply data but no market value.
Questions
How big is the US power transformer market?
Mordor Intelligence values it at $4.49bn in 2025, rising to $6.39bn by 2031. The wider US transformer market, including distribution units, was about $12.2bn in 2024 according to Research and Markets.
Is there a transformer shortage in the US?
Yes. Wood Mackenzie expects supply to fall 30% short of demand for power transformers and 10% short for distribution transformers in 2025.
How long does it take to get a power transformer?
Average lead times were 128 weeks for power transformers and 144 weeks for generator step-up units in Wood Mackenzie's second-quarter 2025 survey, as reported by POWER Magazine.
How much of US transformer supply is imported?
Wood Mackenzie estimates imports will make up about 80% of US power transformer supply and 50% of distribution transformer supply in 2025.
Sources
- United States Power Transformer Market, Mordor Intelligence, updated 6 August 2026.
- U.S. Transformer Market Report 2025: $25.7 Bn Opportunities, Research and Markets via GlobeNewswire, 11 April 2025.
- U.S. Power Transformer Market Outlook, DataM Intelligence, updated 26 October 2026.
- Power transformers and distribution transformers will face supply deficits of 30% and 10% in 2025, Wood Mackenzie, 14 August 2025.
- Transformers in 2026: Shortage, scramble, or self-inflicted crisis?, POWER Magazine, 2 January 2026.
- How many transformers will the US distribution grid need by 2050?, NREL, 4 March 2024.
- R&D Efforts to Address Transformer Supply, US Department of Energy, 21 February 2024.