United States utility-scale battery storage market size 2025

The US added a record 15 GW of utility-scale battery storage in 2025, taking the fleet to 43.6 GW, according to EIA. Developers plan 24 GW more in 2026, over half of it in Texas. Here are the EIA, Wood Mackenzie and interconnection-queue numbers.

High confidenceResearched 2 November 20266 linked sources
Market size 2025
15 GW added
Range
15 GW (EIA, utility-scale) – 18.9 GW (Wood Mackenzie/ACP, all segments)
Forecast
24 GW planned for 2026 (EIA); more than 105 GW operating by end-2028
Growth
about 70% a year in installed capacity over 2023–2025 (EIA)

Market size

This market is best measured in capacity, not dollars. The US Energy Information Administration (EIA) reports that 15 GW of utility-scale battery storage came online in 2025, a record, taking operating capacity to 43.6 GW at the end of the year. Another 8.3 GW arrived in the first half of 2026, taking the fleet to nearly 52 GW. EIA says capacity has grown about 70% a year over the past three years.

Wood Mackenzie and the American Clean Power Association (ACP) count 18.9 GW for 2025, up 52%, because their Energy Storage Monitor also includes residential and commercial systems. Their fourth quarter alone was a record 5.8 GW, 4.9 GW of it utility-scale.

MeasureFigurePeriodSource
Utility-scale battery additions15 GW2025EIA
All-segment storage additions18.9 GW (+52%)2025Wood Mackenzie / ACP
Operating utility-scale capacity43.6 GWend 2025EIA
Operating utility-scale capacitynearly 52 GWJune 2026EIA
Planned utility-scale additions24 GW2026EIA
Storage in interconnection queuesabout 749 GWend 2025Berkeley Lab

Where it is being built

  • Texas dominates. Of the 24 GW planned for 2026, Texas accounts for 12.9 GW (53%), California 3.4 GW (14%) and Arizona 3.2 GW (13%). EIA expects ERCOT storage to grow from 15 GW in 2025 to 37 GW by the end of 2027.
  • Second-largest source of new capacity. EIA's 86 GW of planned 2026 additions splits into solar 43.4 GW (51%), batteries 24 GW (28%), wind 11.8 GW and gas 6.3 GW.

The pipeline and FERC

  • Berkeley Lab's Queued Up 2026 counts about 1,312 GW in US interconnection queues at the end of 2025: about 749 GW storage (down 16%), 773 GW solar, 220 GW wind and 253 GW gas (up 86%).
  • Only 13% of capacity that requested interconnection in 2000–2020 had been built by the end of 2025; 75% was withdrawn. Projects built in 2025 took a median of over five years from request to operation.
  • FERC Order 2023 requires cluster studies, proof of site control and higher withdrawal penalties. It was adopted when the queue stood at 2,598 GW, 95% of it renewables or storage.
  • Wood Mackenzie reports utility-scale system prices rose 23% in 2025 and flags foreign-entity-of-concern tax-credit rules as the main policy risk, but no longer expects a near-term contraction.

How this estimate was made

  1. The headline is EIA's 15 GW of utility-scale additions in 2025, from its Preliminary Monthly Electric Generator Inventory, in GW of power capacity, not GWh.
  2. The upper end of the range is Wood Mackenzie/ACP's 18.9 GW, which includes residential and commercial storage: a different scope, not a disagreement.
  3. Cumulative capacity and the 2026 plan come from two EIA Today in Energy articles. Adding EIA's planned 54 GW for H2 2026 to 2028 (14, 26 and 14 GW) to the June 2026 fleet gives EIA's "more than 105 GW by end-2028".
  4. Queue figures are from Berkeley Lab; queued capacity is not a forecast, since most of it is withdrawn.
  5. We give no dollar market size. Wood Mackenzie's five-year outlook (about 500 GWh installed in 2026–2031) sits behind a paywall, so we cite only the headline.

Questions

How much battery storage did the US add in 2025?

EIA counts 15 GW of utility-scale battery storage added in 2025, a record. Wood Mackenzie and ACP count 18.9 GW across all segments including homes and businesses.

How much battery storage does the US have?

43.6 GW of utility-scale batteries were operating at the end of 2025 and nearly 52 GW by June 2026, according to EIA. Developers plan 54 GW more between July 2026 and the end of 2028.

Which state has the most battery storage?

Texas. It accounts for 12.9 GW, or 53%, of the 24 GW planned for 2026, and EIA expects ERCOT storage to reach 37 GW by the end of 2027. California and Arizona follow.

How much storage is waiting in interconnection queues?

About 749 GW at the end of 2025, according to Berkeley Lab, out of 1,312 GW in queues. Historically only 13% of queued capacity has been built.

Sources

  1. Solar and battery storage to lead new US generating capacity additions in 2026, US Energy Information Administration, 20 February 2026.
  2. US battery storage capacity continues rapid growth, US Energy Information Administration, 7 August 2026.
  3. US battery storage capacity grows 70% annually over the past three years, pv magazine USA (reporting EIA data), 12 August 2026.
  4. 2025 US energy storage installations set new record, surpass 2024 by 52%, Wood Mackenzie and American Clean Power Association, 24 March 2026.
  5. Queued Up: 2026 edition, characteristics of power plants seeking transmission interconnection as of the end of 2025, Lawrence Berkeley National Laboratory, 30 June 2026.
  6. FERC Order 2023 and the interconnection queue, Utility Dive, 20 May 2024.

This is an independent desk estimate by The Decision Pattern, built from the public sources linked above and researched on 2 November 2026. The full report builds its own three-method model with the latest evidence, so its figures can differ.