Baseline

Planning & decisions

A baseline is an approved reference version of scope, schedule, cost, benefits, or another controlled plan against which actual performance and proposed change are compared. It records the authorised expectation at a stated point, including its assumptions and version.

By The Decision Pattern · Updated

A question to consider

Which approved reference should this actual result or proposed change be assessed against?

Why it matters

Without a stable reference, teams cannot distinguish performance variance from a changed plan. A baseline supports accountability, forecasting, trend analysis, change control, and an honest history of what leaders approved.

How it works

Complete the relevant planning work, reconcile linked scope, schedule, cost, and resource assumptions, obtain authorised approval, freeze a version and date, measure actuals against it, and process revisions through documented change control.

How to interpret it

The baseline is historical governance evidence, not the latest prediction. A current forecast can move as reality changes while the baseline remains until an approved rebaseline records a legitimate new commitment.

Common mistake

Overwriting the baseline whenever performance slips, or comparing actuals with a moving forecast and calling the gap a variance. This erases accountability and hides the scale and timing of change.

Put it to work

Name the baseline type, owner, approval date, assumptions, and version; preserve prior versions; report actual, baseline, and current forecast together; and explain every approved change.

A practical example

Illustrative example: the approved cost baseline is ₹1.2 crore by 31 March; the current forecast is ₹1.35 crore, so the ₹15 lakh expected overrun remains visible pending any authorised rebaseline.

Questions worth asking

Is a baseline the same as a forecast?

No. A baseline is an approved reference; a forecast is the latest evidence-based expectation of what will happen.

When is rebaselining appropriate?

Use authorised rebaselining after a material approved change, while preserving prior baselines and explaining the decision and impact.

Sources & further reading

Explore the background to this term. Worked examples on this page are illustrative.