the decision pattern.TDP.

Schedule variance

Planning & decisions

In earned value management, schedule variance is earned value minus planned value at a common status date: SV = EV − PV. It expresses the budgeted value of work ahead of or behind plan, not calendar days, and normally tends toward zero at project completion.

By The Decision Pattern · Updated

A question to consider

Which incomplete planned work creates the variance, and does its schedule logic threaten the committed finish?

Why it matters

The metric shows whether the project has completed more or less budgeted work than planned by the status date. It creates an early performance signal when paired with valid schedule logic.

How it works

Use the authorised time-phased baseline, verify objective completion, calculate EV and PV at the same cut-off, subtract PV from EV, and report the currency or budget units, sign convention, percentage, and affected work.

How to interpret it

Negative SV means less budgeted work was earned than planned; positive means more. It does not state how many days late the finish is or whether delayed work sits on the critical path.

Common mistake

Translating a −₹2 lakh schedule variance directly into two weeks of delay, or averaging unlike projects. Calendar impact requires the network schedule, remaining durations, dependencies, and critical path.

Put it to work

Trace variance to work packages, inspect the current critical path and milestones, verify data timing, choose recovery actions, and update the forecast rather than managing the number alone.

A practical example

Illustrative example: EV is ₹8 lakh and PV is ₹10 lakh at 31 August, so SV = ₹8 lakh − ₹10 lakh = −₹2 lakh of budgeted work.

Questions worth asking

Is schedule variance measured in days?

Not in EVM. SV uses budget units because it subtracts planned value from earned value at the status date.

Why can schedule variance become zero at completion?

Once all authorised work is earned, earned value equals total planned value even if the project actually finished late.

Sources & further reading

Explore the background to this term. Worked examples on this page are illustrative.

Put the thinking to work.

Explore the question with Research Reports. Write, model and review your decision paper with Executive Editor.

Find your reportExplore Executive Editor