Distribution requirements planning
Cash & operations
Distribution requirements planning (DRP) is a time-phased inventory replenishment method that applies Material Requirements Planning (MRP) logic across a multi-echelon distribution network—translating regional warehouse forecasts, safety stock targets, and transit lead times into scheduled replenishment shipments from central distribution centers and factories.
By The Decision Pattern · Updated
A question to consider
Do our central production planners see time-phased future replenishment needs across every regional warehouse, or are they surprised by batch reorders?
Why it matters
When regional warehouses reorder independently using simple min/max reorder points without visibility into upstream factory schedules, three regional depots can simultaneously trigger large batch orders in the exact same week—creating an artificial bullwhip spike at the central plant when end-customer demand barely moved. DRP replaces blind reactive reorder points with forward time-phased visibility across every echelon.
How it works
At each regional distribution center (DC), DRP maintains a time-phased grid by SKU showing Gross Requirements (customer orders and local forecasts), Scheduled Receipts (in-transit shipments), Projected On-Hand Balance, and Planned Order Releases offset by transit and handling lead time. Those Planned Order Releases from all regional DCs roll up directly into the Gross Requirements of the central supply source or Master Production Schedule (MPS).
How to interpret it
Unlike reorder-point systems that wait until stock drops below a threshold today to shout for an order, DRP projects net requirements 4 to 12 weeks ahead, allowing logistics planners to consolidate planned SKU releases into full-truckload shipments and allocate scarce factory output fairly when supply is short.
Common mistake
Letting each regional branch manager pad their local DRP forecast or safety stock independently during a tight supply period, which amplifies phantom demand at the factory.
Put it to work
Link regional warehouse time-phased net requirements directly into the central DC and Master Production Schedule, use DRP planned orders to build full-truckload multi-SKU replenishment loads, and centralize allocation rules when factory supply is constrained.
A practical example
Illustrative example: three regional depots each need a 400-unit pallet of SKU-90 within the next three weeks; DRP projects the exact week each depot crosses its safety-stock floor (Weeks 1, 2, and 3) so the central plant schedules three level 400-unit weekly runs instead of facing a surprise 1,200-unit rush order.
Questions worth asking
How does distribution requirements planning (DRP) differ from reorder point (ROP) replenishment?
Reorder point triggers an order only after current inventory drops to a threshold, whereas DRP projects future time-phased demand, scheduled receipts, and planned orders across multiple future periods.
How does DRP connect to the Master Production Schedule (MPS)?
Planned order releases from regional distribution centers roll up by date to become the gross distribution demand feeding the central plant's Master Production Schedule.
Sources & further reading
Explore the background to this term. Worked examples on this page are illustrative.
- Martin — Distribution Resource Planning: The Gateway to True Quick Response and Continual Replenishment (Oliver Wight Publications)
Time-phased multi-echelon DRP logic, rollup of planned shipments into central supply schedules, and freight consolidation.