Material requirements planning
Cash & operations
Material requirements planning is a time-phased method that uses the master production schedule, bills of material, inventory records, lead times, and order rules to calculate component requirements and recommend new or rescheduled supply orders.
By The Decision Pattern · Updated
A question to consider
Which component orders must be released or rescheduled to support the authorized production plan on time?
Why it matters
Finished-product plans translate into many dependent component needs at different dates. MRP coordinates that explosion so teams can reduce avoidable shortages, excess stock, and manual expediting across complex assemblies.
How it works
Start with approved end-item quantities and dates, explode each bill of material, net gross requirements against usable on-hand and scheduled receipts, apply lead times and lot-sizing rules, and create planned-order receipts and releases. Re-run after controlled changes.
How to interpret it
MRP output is a recommendation based on input accuracy and assumed lead times, yields, and capacity. Nervous schedules, obsolete bills, incorrect status, and unrealistic dates can create precise but unusable orders.
Common mistake
Treating every planned order as an automatic purchase commitment or using MRP as a demand forecast. It converts an authorized production plan into dependent requirements; it does not validate market demand or finite capacity.
Put it to work
Audit bills, inventory status, lead times, yields, and planning parameters; govern schedule changes; review exception messages; confirm capacity and supplier feasibility; and measure shortages, excess, and rescheduling caused by input error.
A practical example
Illustrative example: 100 finished units due in week six require two components each; after netting 30 usable units on hand, MRP plans 170 component receipts and offsets the release by lead time.
Questions worth asking
Is MRP a demand forecast?
No. It consumes a production schedule and product structure to calculate dependent material needs; the demand input must be planned separately.
Does MRP check production capacity?
Basic MRP focuses on material timing; capacity planning and execution checks are still needed before recommendations become feasible commitments.
Sources & further reading
Explore the background to this term. Worked examples on this page are illustrative.
- ASCM — Supply Chain Dictionary, 18th edition
Definitions and operating context for inventory, planning, service, production, quality, flow, and supplier-management concepts.
Source checked
Put the thinking to work.
Explore the question with Research Reports. Write, model and review your decision paper with Executive Editor.
Find your reportExplore Executive Editor