Earned value management
Planning & decisions
Earned value management, or EVM, integrates approved scope, schedule, and cost baselines to compare planned value, earned value, and actual cost at a common status date. It quantifies budgeted value of completed work rather than relying on money spent or subjective percent complete.
By The Decision Pattern · Updated
A question to consider
How much authorised work was actually completed for the cost incurred by the common status date?
Why it matters
EVM can reveal cost and schedule performance before final overruns appear by asking how much budgeted work was planned, completed, and paid for. It also provides a consistent basis for forecasting.
How it works
Define measurable work packages, time-phase the authorised budget, choose objective earning rules, record actual cost in the same structure and period, calculate variances and indices, forecast outcomes, and maintain baseline change control.
How to interpret it
Results depend on baseline quality, status discipline, and honest completion evidence. Level-of-effort work, late actual costs, inappropriate earning rules, and authorised scope changes can distort apparent performance.
Common mistake
Calling budget spent ‘earned value’ or assigning 90% complete repeatedly without objective evidence. Spending measures consumption; earned value measures the budgeted value of completed authorised work.
Put it to work
Pilot EVM on material work packages, align finance and schedule cut-offs, audit earning evidence, explain variance drivers and critical-path effects, and update the estimate at completion.
A practical example
Illustrative example: at month end, planned value is ₹10 lakh, earned value ₹8 lakh, and actual cost ₹9 lakh; schedule variance is −₹2 lakh and cost variance −₹1 lakh.
Questions worth asking
Is earned value the revenue a project generated?
No. It is the approved budgeted value assigned to completed project work, independent of customer revenue or invoice value.
Can EVM work without a reliable baseline?
No. Weak scope, schedule, budget, or change control makes the calculated precision misleading and limits useful forecasting.
Sources & further reading
Explore the background to this term. Worked examples on this page are illustrative.
- U.S. GAO — Cost Estimating and Assessment Guide
Earned value management and schedule variance as earned value minus planned value, expressed in budget units and interpreted with schedule logic.