Input-output control

Cash & operations

Input-output control is a shop-floor capacity execution and queue-management technique originally formulated by Oliver Wight that monitors planned versus actual work hours released into a work center (input), completed by the work center (output), and waiting in queue—preventing work-in-process bloat and lead-time inflation.

By The Decision Pattern · Updated

A question to consider

Is the queue at this work center growing because upstream is releasing too much work (input variance) or because the station is under-producing (output variance)?

Why it matters

Capacity Requirements Planning (CRP) is only a plan on paper. In actual execution, if upstream departments release 130 standard hours of jobs per week into a machining center that only completes 105 standard hours per week, the queue in front of that work center grows by 25 hours every single week. By Little's Law, growing queues directly lengthen manufacturing lead times and cause late deliveries.

How it works

For each constrained or gateway work center, track a weekly Input-Output Report with five rows expressed in standard hours: (1) Planned Input, (2) Actual Input (work arriving from upstream or order release), (3) Planned Output, (4) Actual Output (standard hours completed), and (5) Actual Queue (Ending Queue = Beginning Queue $+$ Actual Input $-$ Actual Output). Enforce the golden rule of input-output control: never release more work into the gateway than the work center is actually completing, unless you are deliberately building a planned buffer.

How to interpret it

Separating Input Variance (Actual Input $-$ Planned Input) from Output Variance (Actual Output $-$ Planned Output) immediately pinpoints root cause: if queues are rising because Actual Input exceeded plan, upstream release discipline failed; if Actual Input matched plan but Actual Output fell short, the work center itself suffered downtime, staffing shortages, or quality rework.

Common mistake

Releasing new work orders onto the shop floor "on schedule" when the downstream work center's actual output is running 20% below plan—which only clogs the floor with WIP without producing one extra finished unit.

Put it to work

Choke order release at the gateway work center so weekly input hours never exceed demonstrated weekly output hours, set a maximum tolerance band on work-center queue hours, and review Input-Output variance reports weekly to fix capacity shortfalls before queues explode.

A practical example

Illustrative example: a grinding center starts with a 40-hour queue and plans 100 hours of input and 100 hours of output per week; when machine maintenance drops actual output to 80 hours for two weeks while upstream keeps releasing 100 hours, the queue balloons to 80 hours—doubling lead time from 2 days to 4 days.

Questions worth asking

What is the fundamental rule of input-output control?

Put in no more work than the work center can get out: control lead times and work-in-process queues by throttling order release to match actual demonstrated output.

How is ending queue calculated on an input-output control report?

Ending Queue equals Beginning Queue plus Actual Input minus Actual Output, all measured in standard work hours.

Sources & further reading

Explore the background to this term. Worked examples on this page are illustrative.