Capacity requirements planning

Cash & operations

Capacity requirements planning (CRP) is the detailed, time-phased operational planning process that translates both open shop-floor work orders and Material Requirements Planning (MRP) planned order releases into exact setup and run-hour loads by work center and time bucket, comparing required load against rated capacity.

By The Decision Pattern · Updated

A question to consider

When we combine open shop orders with MRP planned releases and setup times, which work centers exceed their rated weekly capacity?

Why it matters

Even when Rough-Cut Capacity Planning (RCCP) confirms that average monthly bottleneck capacity is sufficient for the Master Production Schedule, lot-sizing rules, existing work-in-process queues, and offset component lead times can create severe week-by-week load spikes at non-bottleneck work centers. CRP exposes those exact weekly or daily load imbalances across every work center.

How it works

CRP takes four inputs: (1) MRP planned order releases and scheduled receipts (open shop orders), (2) part routings specifying the sequence of work centers, setup times, and run times per piece, (3) work-center calendar files specifying available shifts, utilization, and efficiency (Rated Capacity = Shifts $\times$ Hours $\times$ Utilization $\times$ Efficiency), and (4) standard queue, wait, and move times. Using backward scheduling from each order's due date, CRP generates a Work Center Load Profile showing required hours versus available capacity per period.

How to interpret it

Because standard CRP assumes infinite capacity when building the initial load profile, periods where the load bar exceeds the rated-capacity line require finite resolution: splitting lots, shifting orders earlier into underloaded weeks, rerouting to alternate machines, authorizing overtime, or subcontracting.

Common mistake

Ignoring setup hours in CRP load calculations when lot sizes are cut in half—causing actual shop load to exceed planned load and stalling flow.

Put it to work

Keep part routings, setup standards, and work-center utilization/efficiency factors updated from actual shop-floor data; review CRP load profiles weekly over the slushy and frozen time horizons; and resolve overloads via lot splitting, alternate routings, or short-term overtime before releasing orders to the floor.

A practical example

Illustrative example: detailed CRP reveals that three batch orders converging in Week 3 require 148 setup-and-run hours on Work Center 14 against 120 hours of rated capacity, while Week 2 has only 82 hours loaded; pulling one planned order forward into Week 2 levels the load without overtime.

Questions worth asking

Why does CRP account for existing inventory and lot sizes while RCCP does not?

CRP runs after Material Requirements Planning (MRP), so it uses net planned orders and actual open work orders rather than top-level finished-goods schedule quantities.

How is rated capacity calculated for a work center in CRP?

Multiply available clock hours (machines $\times$ shifts $\times$ hours) by historical utilization (fraction of time actually running) and efficiency (standard hours earned divided by actual run hours).

Sources & further reading

Explore the background to this term. Worked examples on this page are illustrative.