the decision pattern.TDP.

Pegging

Cash & operations

Pegging is the traceability capability in a material requirements planning (MRP) or supply-chain system that links a lower-level component requirement, work order, or purchase order upward through each level of the bill of materials to identify the exact parent production order, customer sales order, or forecast line that generated the demand.

By The Decision Pattern · Updated

A question to consider

Which specific customer orders or forecast lines are actually waiting on this delayed component, and do any of them justify paying to expedite?

Why it matters

Because MRP nets and batches component requirements across dozens of finished products at each level of the bill of materials, when a supplier calls to say a shipment of bearings will be five days late, a planner looking only at the bearing item record cannot tell whether that delay affects a low-priority stock refill or a penalty-clause hospital order. Pegging traces the shortage straight up to the affected top-level customer orders.

How it works

Single-level pegging traces a component requirement one rung up the bill of materials to its immediate parent subassembly. Full (or multi-level / end-item) pegging traces all the way up the BOM tree to the originating master production schedule item or customer sales order. Hard pegging permanently locks specific lot or serial numbers of inventory and purchase orders to a single customer contract (common in aerospace and defense), while soft pegging recalculates allocations dynamically as priorities shift.

How to interpret it

Use soft pegging in standard commercial manufacturing so scarce components can be reassigned to the highest-priority customer order when a shortage hits; reserve hard pegging for regulated or customer-funded contracts where contract law forbids commingling stock.

Common mistake

Expediting every late supplier purchase order at high air-freight cost without checking pegging first—when half of those late components are pegged only to safety-stock replenishment or deferred customer orders.

Put it to work

Require planners to check multi-level pegging before paying expedite fees or approving overtime, use pegging impact reports to notify affected customers proactively when a critical supplier slips, and avoid hard pegging on fungible commercial parts.

A practical example

Illustrative example: when a PCB vendor delays 500 controller boards by 8 days, multi-level pegging shows 350 boards are pegged to a Q3 distributor stock forecast while only 150 are pegged to next week's confirmed customer orders—allowing the buyer to air-freight just the 150 urgent boards and save $6,400.

Questions worth asking

How is pegging different from a where-used report?

A static where-used report lists every product whose bill of materials contains the part in general, whereas pegging identifies the specific active orders that generated today's open requirement.

What is the difference between hard pegging and soft pegging?

Hard pegging permanently locks a specific purchase or work order to one customer contract, while soft pegging dynamically links requirements to demand so planners can reallocate stock.

Sources & further reading

Explore the background to this term. Worked examples on this page are illustrative.

Put the thinking to work.

Explore the question with Research Reports. Write, model and review your decision paper with Executive Editor.

Find your reportExplore Executive Editor