Rough-cut capacity planning
Cash & operations
Rough-cut capacity planning (RCCP) is a medium-term planning step that converts the Master Production Schedule (MPS) of finished goods directly into aggregate load hours on critical bottleneck work centers, key suppliers, and specialized labor skills—verifying that the master schedule is feasible before running detailed Material Requirements Planning (MRP).
By The Decision Pattern · Updated
A question to consider
Does our Master Production Schedule fit within the demonstrated weekly capacity of our bottleneck work centers before we release component purchase orders?
Why it matters
Running a full multi-level Material Requirements Planning (MRP) explosion and launching thousands of component purchase orders for a Master Production Schedule that exceeds your heat-treat furnace or test-bench capacity by 40% simply floods the shop floor with raw materials you cannot process. RCCP acts as a fast gatekeeper on the MPS using a small set of critical resources.
How it works
Rather than exploding every subassembly and open work order across all 200 shop work centers (which is the job of detailed Capacity Requirements Planning, CRP), RCCP uses a Bill of Resources (or Capacity Bill) for each end-item product family. The Bill of Resources states the total standard hours required per finished unit on the 3 to 8 designated critical/bottleneck resources. Multiplying the weekly MPS quantities by the Bill of Resources yields required weekly bottleneck hours, which are compared against demonstrated capacity.
How to interpret it
When RCCP shows that a critical resource is overloaded in Week 6, planners have two choices before releasing the MPS to MRP: increase capacity (overtime, extra shifts, subcontracting) or level/reschedule the MPS quantities across earlier or later weeks.
Common mistake
Comparing RCCP load against theoretical nameplate capacity (24 hours $\times$ 7 days) instead of demonstrated historical capacity adjusted for utilization, efficiency, and planned maintenance.
Put it to work
Maintain a concise Bill of Resources for your top bottleneck work centers and long-lead vendor processes, run RCCP automatically whenever the Master Production Schedule changes, and never release an overloaded MPS into detailed MRP execution.
A practical example
Illustrative example: a pump manufacturer's Q3 Master Production Schedule calls for 400 heavy pumps per week; RCCP multiplies 400 units by 0.65 test-stand hours per pump (260 hours required) against 200 demonstrated test-stand hours available—catching a 30% bottleneck overload 8 weeks ahead so a weekend test shift can be added.
Questions worth asking
How does rough-cut capacity planning (RCCP) differ from capacity requirements planning (CRP)?
RCCP checks only critical bottleneck resources directly against the top-level Master Production Schedule before MRP runs, whereas CRP checks all work centers using detailed time-phased MRP planned orders and open shop orders.
What is a Bill of Resources in RCCP?
A table listing the aggregate hours of each critical bottleneck resource required to produce one unit of a finished product or product family across all bill-of-material levels.
Sources & further reading
Explore the background to this term. Worked examples on this page are illustrative.
- Jacobs, Berry, Whybark, and Vollmann — Manufacturing Planning and Control for Supply Chain Management (Rough-Cut Capacity Planning)
RCCP validation of the Master Production Schedule using Bills of Resources on critical bottleneck work centers prior to MRP.