Time fence
Cash & operations
A time fence is a policy boundary on the master production schedule (MPS) horizon that divides future planning periods into distinct zones—typically Frozen, Slushy, and Liquid—with progressively stricter approval rules governing what schedule, quantity, or product-mix changes are permitted as the production date approaches.
By The Decision Pattern · Updated
A question to consider
Within how many weeks of production are materials and capacity already committed such that schedule changes destroy more value than they capture?
Why it matters
If sales or executives can insert rush orders or cancel quantities inside next week's production schedule at will, the factory suffers constant emergency setups, stranded raw materials, expediting fees, and missed dates on other customers' orders ("schedule nervousness"). Conversely, locking the schedule six months out makes the business unresponsive. Time fences balance stability inside lead times against flexibility further out.
How it works
Define two primary boundaries on the rolling horizon: (1) the Demand Time Fence (inside which the schedule is "Frozen"—materials are already cut and capacity is committed, so only actual customer orders are counted and changes require executive sign-off with cost impact), and (2) the Planning Time Fence, typically set at cumulative procurement plus manufacturing lead time (between the Demand and Planning fences is the "Slushy" zone, where product mix can shift within fixed capacity and common materials; beyond the Planning fence is the "Liquid" zone, where any forecast or capacity change is allowed).
How to interpret it
A frozen zone does not mean an emergency change is physically impossible; it means the change cannot happen silently via an automated MRP run—it forces a formal trade-off showing which existing order will be delayed and what scrap or expedite cost will be incurred.
Common mistake
Setting a 4-week frozen time fence when critical components have an 8-week non-cancelable supplier lead time, or allowing sales managers to override the frozen zone routinely without charging the expedite cost to the order.
Put it to work
Align your Planning Time Fence with cumulative critical-path lead time and your Demand Time Fence with final assembly cycle time, configure ERP auto-rescheduling to stop outside the frozen fence, and log every frozen-zone exception cost.
A practical example
Illustrative example: an industrial pump maker sets a 2-week Frozen fence (final assembly), a 6-week Slushy fence (machining and subassembly), and a Liquid zone beyond Week 6; a customer request in Week 3 to swap motor voltages within the same pump frame is approved in the Slushy zone without delaying the ship date.
Questions worth asking
What are the three zones created by time fences in a master schedule?
The Frozen zone (inside the demand time fence), the Slushy or Firm zone (between the demand and planning time fences), and the Liquid or Free zone (beyond the planning time fence).
How do time fences reduce MRP schedule nervousness?
By blocking automated forecast fluctuations from altering near-term planned orders inside the frozen and slushy zones, preventing cascading reschedule notices to suppliers and shop floors.
Sources & further reading
Explore the background to this term. Worked examples on this page are illustrative.
- Vollmann, Berry, Whybark, and Jacobs — Manufacturing Planning and Control for Supply Chain Management (Time Fences)
Demand and planning time fences, frozen/slushy/liquid master schedule zones, and dampening of MRP schedule nervousness.
Source checked