How do you compare projects when one consumes a scarce specialist team?

Estimate comparable project value and the specialist capacity each project needs, then evaluate feasible combinations within the actual resource and timing constraints. Value per specialist week can be informative, but it is not generally a sufficient selection rule for indivisible projects. Check dependencies, mandatory work, calendars, uncertainty, and the cost of genuinely expanding capacity.

The short answer

Estimate comparable project value and the specialist capacity each project needs, then evaluate feasible combinations within the actual resource and timing constraints. Value per specialist week can be informative, but it is not generally a sufficient selection rule for indivisible projects. Check dependencies, mandatory work, calendars, uncertainty, and the cost of genuinely expanding capacity.

Key takeaways

  • Choose a feasible combination of projects rather than assuming individual rankings solve the allocation.
  • A ratio can fail when indivisible projects leave unusable capacity.
  • Specialist weeks must represent the required skills and dated availability.
  • Additional capacity has value only if it changes the feasible choices and can actually be supplied.

Three projects look attractive, but all require the same specialist team during the planning window. The sponsor proposes funding the project with the highest value, while another manager suggests ranking value per specialist week.

Both comparisons contain useful information. Neither necessarily identifies the best feasible combination when projects cannot be divided into arbitrary fractions. The decision is about a portfolio under constraints.

Define the constrained resource precisely

Specify the skill, authorization, and calendar availability that projects require. A generic person-week is insufficient if only particular people can perform or approve the work.

Deduct existing commitments, required operating work, and unavailable periods before allocating new projects. Confirm whether estimates include review, coordination, correction, and transition effort.

For the illustration, assume one interchangeable specialist resource has ten usable weeks in the relevant window. Other necessary resources are available, and each selected project can be scheduled within that window. These simplifying assumptions must be tested in a real case.

Put project values on a comparable basis

Use the same perspective, timing basis, and treatment of costs across projects. Here, the values are hypothetical incremental net present values already calculated consistently.

Do not compare one project’s revenue with another’s profit or one option’s gross benefits with another’s value after costs. Also identify benefits shared across projects so they are not counted twice.

Three fictional indivisible projects competing for ten specialist weeks
ProjectComparable valueSpecialist weeksValue per specialist week
A80,0006Approximately 13,333
B65,000513,000
C60,000512,000

A ranks first by both individual value and value per week. Selecting A uses six weeks and leaves four, which is insufficient for either B or C under the indivisibility assumption.

Enumerate the feasible combinations

Google’s explanation of the knapsack problem describes selecting a maximum-value subset subject to a capacity limit. The same simplified structure can help reason about independent, indivisible projects.

Feasibility and value under the fictional ten-week limit
SelectionWeeks requiredValueFits the capacity limit?
None00Yes
A680,000Yes
B565,000Yes
C560,000Yes
A and B11145,000No
A and C11140,000No
B and C10125,000Yes
A, B, and C16205,000No

B and C together produce 125,000 of modeled value, compared with 80,000 from A alone. The difference is 45,000. A ranking by the best ratio would miss this combination if it simply selected A first and stopped when nothing else fit.

The example demonstrates a limitation of that rule; it does not imply that ratio analysis is always useless. Its adequacy depends on whether work is divisible and on the other constraints and relationships.

Check whether projects are genuinely indivisible

A project may have a smaller stage that creates a useful outcome. If so, define that stage as a separate option with its own value, resource needs, dependencies, and remaining commitment.

Do not assume half a project produces half its value. A partially completed compliance process, migration, or launch may produce little usable benefit and still require substantial follow-on work.

Keep deferred work visible rather than treating it as canceled cost. The guide on deferred investment helps assess what changes when work moves to a later window.

Add the constraints the simple example omits

Identify mandatory projects, deadlines, precedence relationships, budget limits, incompatible changes, and shared benefits. A project that must precede another changes which combinations are feasible.

Check the calendar, not just the total. Ten weeks of work cannot necessarily fit ten available weeks if a project needs a particular specialist during a period when that person is already committed.

Where the problem becomes large, use an appropriate scheduling or optimization method with reviewable inputs. A solver can find a result within its model; it cannot establish that omitted constraints or optimistic values are correct.

Check that the option set is complete

The four weeks left after selecting A are unusable for B or C, but they may have another valuable use. The example assumes the three projects form the complete discretionary choice set; the real organization should test that assumption.

Suppose a separately defined project D becomes available with a comparable value of 50,000 and a requirement of four specialist weeks. A and D would then fit the ten-week limit and produce 130,000, exceeding B and C by 5,000. This does not invalidate the earlier arithmetic; it changes the options the model was allowed to consider.

Look for genuinely feasible smaller projects, operating improvements, or staged options, while checking that their benefits are incremental and their resource estimates complete. Do not create artificial fragments simply to fill the calendar. The value comes from an achievable outcome, not from reporting every specialist as fully occupied.

Evaluate additional capacity as an option

If the limit increases to eleven genuinely usable weeks, A and B become feasible with a modeled value of 145,000. Relative to the best ten-week combination, that is an increase of 20,000.

This is the gross modeled value of that particular capacity change under the assumptions, before the cost and consequences of obtaining it. It is not a universal weekly rate or a promise that one contractor-week creates the same result.

Check availability, skills, onboarding, supervision, approvals, and timing. Additional nominal capacity that arrives after the deadline or consumes equivalent specialist supervision may not expand the feasible set.

Stress-test the recommendation

Vary the uncertain project values and resource estimates that could change the selected combination. Ask what happens if a project needs another week, delivers less benefit, or depends on work outside the current plan.

Record these conditions in the assumption register. The guide on vendor-supplied assumptions is useful where delivery effort or benefits come from a party with a commercial interest.

Within capital allocation, prepare the feasible combinations, resource calendar, and sensitivity in the Executive Editor. The resulting request should identify the portfolio the organization can actually deliver, including the assumptions that make it preferable.

Sources & further reading

  1. Google OR-Tools: The Knapsack Problem

    Describes selecting a subset of indivisible items with maximum total value subject to a capacity bound; the project example is an original adaptation.

Browse more guides
One platform. Two tools.

Research the question.
Build the case.

Use Research Reports to understand the opportunity. Use Executive Editor to develop the recommendation, examine the assumptions and prepare a decision paper.

Research Reports

Explore markets, competitors, customers, brand perception or a product idea. Each one is a complete Standard report.

AI-assisted desk research · One-time report purchaseExplore Research Reports

Executive Editor

Write your case, connect evidence and calculations, review proposed changes and publish a saved version when you are ready.

Use your TDP account · No report purchase requiredExplore Executive Editor