Periodic Review Policy Guide: Calculating the Order-Up-To Level When Inventory Is Checked on a Schedule
How to set the order-up-to level when inventory is reviewed on a fixed schedule, and why periodic review needs more safety stock than continuous review.
The short answer
The order-up-to level equals average demand over the review period plus lead time, plus safety stock of z times the demand spread times the square root of review period plus lead time; with demand of 100 a day, spread of 20, a 7-day review, and a 5-day lead time, the level is about 1,314 against a reorder point of 574 for continuous review.
Key takeaways
- Primary measure: Order-Up-To Level, Safety Stock, and Cycle Service Level.
- Healthy: Review period, lead time, and demand variability used to set levels, with service level measured and the review period challenged.
- Watch closely: Levels set from past peaks or rules of thumb, with the review schedule fixed by habit.
- Act now: Orders placed on a schedule without a target level, so stock and service swing with each cycle.
- Weekly review needs 114 units of safety stock against 74 for continuous review, and moving to a 14-day review raises it to 143, so each longer review period carries a measurable inventory cost.
How to set the order-up-to level when inventory is reviewed on a fixed schedule, and why periodic review needs more safety stock than continuous review. Key terms used below: periodic review system, continuous review system, safety stock, cycle service level. Related guides: Safety Stock and Reorder Points: Match the Model to Demand, Lead Time and Service Goals and Economic Production Quantity Guide: Batch Size and Setup Cost Reduction.
What decision this guide supports
Some items are checked on a fixed schedule, such as weekly, because suppliers deliver on set days, orders are consolidated, or counting is costly. At each review, the planner orders enough to bring inventory back to a target level, often called the order-up-to or base-stock level.
Because inventory is not watched between reviews, a stockout can develop unseen. The target must therefore cover demand over the review period plus the replenishment lead time, and it needs safety stock for variability over that whole period.
This is the main difference from continuous review, where an order is triggered the moment stock reaches a reorder point, so safety stock only needs to cover the lead time.
Key terms
- Order-up-to level
- The target inventory position to which stock is brought at each review.
- Review period
- The time between inventory checks and order decisions.
- Inventory position
- On-hand inventory plus on-order inventory minus backorders.
- Cycle service level
- The probability of not stocking out in a replenishment cycle.
How to calculate it
The order-up-to level S equals average daily demand d times review period R plus lead time L, plus safety stock. Safety stock equals z times sigma times the square root of R plus L, where sigma is the standard deviation of daily demand and z gives the target cycle service level. For continuous review, the reorder point equals d times L plus z times sigma times the square root of L. The order placed at each review equals S minus the inventory position.
Benchmark matrix and working thresholds
The table summarizes the main options or components and what to watch in each.
| Policy | Demand Coverage | Safety Stock | Target Level |
|---|---|---|---|
| Continuous review (reorder point) | 500 | 73.6 | 573.6 |
| Periodic review, 7-day period | 1,200 | 114.0 | 1,314.0 |
| Periodic review, 14-day period | 1,900 | 143.4 | 2,043.4 |
Working thresholds
Treat these as starting heuristics to calibrate against your own data, not universal standards.
- Healthy: Review period, lead time, and demand variability used to set levels, with service level measured and the review period challenged.
- Watch closely: Levels set from past peaks or rules of thumb, with the review schedule fixed by habit.
- Act now: Orders placed on a schedule without a target level, so stock and service swing with each cycle.
Worked scenario
The figures below are an illustrative composite, not a named company or an audited case. Replace them with your own data.
Illustrative composite: an item sells 100 units a day on average, with a daily standard deviation of 20. The supplier lead time is 5 days, and the planner wants a 95% cycle service level, so z is 1.645. Under continuous review, demand during the lead time averages 500 units, safety stock is 1.645 times 20 times the square root of 5, which is 73.6, and the reorder point is 573.6. Under a weekly review, protection must cover the 7-day review period plus the 5-day lead time, 12 days in all. Average demand over that period is 1,200 units, and safety stock is 1.645 times 20 times the square root of 12, or 114.0, so the order-up-to level is 1,314. That is 40.4 units, or 55%, more safety stock than continuous review needs, and the planner would order on average 700 units each week, the demand of one review period. If the review period were extended to 14 days to save ordering effort, the covered period would be 19 days, safety stock would be 143.4, and the level 2,043.4. The extra 29.4 units of safety stock is 26% more than under weekly review. The decision to review less often therefore trades lower ordering effort for more stock, which the planner can price using the carrying cost of the item.
What the scenario shows
Weekly review needs 114 units of safety stock against 74 for continuous review, and moving to a 14-day review raises it to 143, so each longer review period carries a measurable inventory cost.
How to read the results
- If safety stock is much higher than under continuous review: The review period is long relative to lead time, so consider a shorter period.
- If stockouts occur more than planned: Check demand variability, lead time reliability, and whether the inventory position is computed correctly.
- If inventory is much higher than needed: The review period or the service target may be too generous for the item's value.
Common failure modes
- Covering only lead time: In periodic review, the protection period is review period plus lead time.
- Ignoring the order-up-to level: Ordering a fixed quantity at each review lets inventory drift away from target.
- Using stale variability estimates: Demand spread changes with promotions and seasons and should be updated.
- Reviewing too rarely for fast movers: Items with high value and high demand may justify more frequent review.
Putting it into practice
- Collect demand and lead time data: Estimate average demand and its standard deviation, and the lead time and its variability.
- Compute levels: Calculate the order-up-to level for the current review period and for alternatives, and price the extra stock.
- Run the policy and measure: Order up to the level at each review, track service level and stock, and adjust the parameters on schedule.
Sensitivity and limits
- Review period: Test review periods of 3, 7, and 14 days.
- Service level: Compare 90%, 95%, and 99% cycle service levels.
- Demand variability: Check the level if the daily standard deviation is 30 instead of 20.
The formulas assume independent, normally distributed daily demand and a constant lead time. Variable lead time, correlated demand, and batch ordering need adjustments, and the cycle service level is not the same as the share of units delivered on time.
Where this fits in a wider decision
Use periodic review for items that share a supplier or delivery day, or where continuous monitoring is costly. Choose the review period by weighing ordering and handling costs against the extra safety stock.
Your checklist
- Confirm you have avoided this trap: Covering only lead time.
- Confirm you have avoided this trap: Ignoring the order-up-to level.
- Confirm you have avoided this trap: Using stale variability estimates.
- Confirm you have avoided this trap: Reviewing too rarely for fast movers.
Steps to follow
Collect demand and lead time data
Estimate average demand and its standard deviation, and the lead time and its variability.
Compute levels
Calculate the order-up-to level for the current review period and for alternatives, and price the extra stock.
Run the policy and measure
Order up to the level at each review, track service level and stock, and adjust the parameters on schedule.
Common questions
How do I calculate the order-up-to level?
Add average demand over the review period plus lead time to safety stock equal to z times the demand standard deviation times the square root of that period.
Why does periodic review need more safety stock?
Because stock must cover variability over the review period as well as the lead time, since no order can be placed between reviews.
Related topics
- periodic review inventory
- order up to level
- base stock policy
- periodic vs continuous review
- safety stock periodic review
- inventory review period
- (r,s) inventory policy
Sources & further reading
- ASCM Supply Chain Resources
Association for Supply Chain Management
Industry definitions for inventory policies and service levels.
- U.S. Census Bureau Manufacturing and Trade Inventories and Sales
U.S. Census Bureau
Aggregate inventory and sales data for context on stock levels.
- NIST Manufacturing Extension Partnership
National Institute of Standards and Technology
Public resources for manufacturers on quality and operational improvement.