Kanban

Cash & operations

Kanban is a controlled signal that authorizes production or movement of a specified item and quantity in a pull system. A card, container, electronic message, or other signal links downstream consumption to upstream replenishment.

By The Decision Pattern · Updated

A question to consider

What signal and work limit will replenish actual consumption without hiding instability in excess inventory or queue length?

Why it matters

Forecast-driven releases can flood a process with work that customers or downstream steps do not yet need. Explicit signals cap work in progress, expose shortages and delays, and connect replenishment to actual consumption.

How it works

Define the supplying and consuming processes, container quantity, signal count, replenishment loop, trigger, ownership, and rules. A withdrawal signal authorizes movement; a production signal authorizes replacement of what was consumed.

How to interpret it

A board showing tasks is not automatically a production kanban system. The operational control comes from explicit authorization and work limits; signal counts embed demand, lead time, variability, and buffer assumptions.

Common mistake

Adding cards while allowing schedulers to release unsignaled work whenever pressure rises. That breaks the limit, hides the constraint, and turns the visual system into decoration.

Put it to work

Start with a stable product family, measure consumption and replenishment time, calculate a conservative loop, label every signal, enforce no-signal rules, track shortages and blocked cards, and reduce buffers only after causes improve.

A practical example

Illustrative example: each empty 20-part container releases one production card upstream, while six circulating cards cap the loop at 120 parts plus defined exceptions.

Questions worth asking

Is kanban the same as a task board?

No. A task board can visualize work, while kanban requires explicit policies and signals that control entry or replenishment.

How many kanban signals are needed?

The count depends on demand during replenishment time, container size, variability, and a deliberately justified safety allowance.

Sources & further reading

Explore the background to this term. Worked examples on this page are illustrative.

  • Lean Enterprise Institute — Kanban

    Kanban as a controlled production or withdrawal signal in a pull system, including the relationship between production and withdrawal signals.